023-3 Wyo. Code R. §§ 3-24 - Transfer of Utility Control; Adoption of Tariffs
(a) Any entity,
including receivers or trustees, proposing to acquire all or partial ownership
or control of a utility, must adopt the tariff of the predecessor utility on
file with the Commission and effective at the time of transfer. The transferee
shall issue and file an adoption notice within 10 days of the transfer,
ratifying the former utility's tariff.
(b) Within 10 days after filing an adoption
notice, the transferee utility, including receivers or trustees, shall issue
and file in its own name the tariff of its predecessor or its proposed revised
tariff.