023-4 Wyo. Code R. §§ 4-5 - Construction and Maintenance Standards
(a) Construction
standards.
(i) Companies shall use the
following safety standards for construction of new facilities:
(A) NESC approved by ANSI, Standard C2;
and
(B) Current accepted
engineering standards for the construction of telecommunications
plant.
(ii) All
telecommunications cables, both direct and in conduit, shall be installed at
least 12 inches below the final surface grade. This requirement is not waived
if a Company opts to install buried cable before the final grade is
established.
(iii) Companies shall
use Part 68, Title 47 of the CFR for the connection of its new or existing
telecommunications plant with terminal equipment of a customer;
(iv) Companies shall coordinate with
utilities and other Companies to avoid or eliminate any interference. The owner
of new facilities interfering with existing facilities constructed in
accordance with relevant and applicable standards shall bear the cost of
correction and mitigation.
(b) Maintenance standards.
(i) Companies shall use the following safety
standards for maintenance and operation of facilities:
(A) The NESC approved by the ANSI, Standard
C2; and
(B) Practices standard in
the industry.
(ii) Each
Company shall adopt and comply with maintenance programs, including periodic
testing, inspections and prevention, to ensure efficient operation of its
system for the rendering of safe, adequate and continuous telecommunications
service.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.