027-9 Wyo. Code R. §§ 9-5 - Determination of Delivery Method
(a) Projects shall be designed and
constructed using the design-bid-build delivery method unless extenuating
circumstances exist that necessitate the adoption of an alternate method.
District requests for the Commission to approve an alternate design and
construction delivery method shall explain the reason(s) an alternate project
delivery method is preferable to the design-bid-build delivery
method.
(b) The Commission shall
consider the following non-exclusive and non-prioritized list of factors in
making a determination to allow alternate design and construction delivery
methods:
(i) Size and complexity of the
remedy;
(ii) Budget and
availability of funds;
(iii)
Urgency of time;
(iv) Past
experience with the delivery method;
(v) Anticipated cost of the possible various
delivery methods;
(vi) Market
conditions, including access to and availability of personnel to provide design
or construction services; and
(vii)
District input and recommendations regarding delivery method.