045-5 Wyo. Code R. §§ 5-6 - License Agreements - Fiber Optics Cables
(a) When a
communications company, federal agency, or other governmental agency approaches
the District regarding the crossing and/or parallel encroachment of fiber
optics facilities, the District shall review their proposed construction,
stipulate changes in the proposed construction method and/or location, and
furnish Form E-54B (Fiber Optics Construction Standard) to the
applicant.
(b) After the Districts
recommendations have been incorporated into the applicants design and all other
provisions of Department regulations have been met, the District will furnish
all pertinent information and exhibits to the Utilities Section in Cheyenne for
preparation of a License Agreement.
(c) In cases where the applicant's proposed
project consists of crossings and/or encroachments in several locations within
a WHD District, one License Agreement may be prepared to cover the entire
District instead of each crossing or encroachment separately, at the discretion
of the District.