048-24 Wyo. Code R. §§ 24-8 - Cost settlement
(a) Cost settlement
methodology. Cost reports shall be cost settled by the Medicare intermediary
using Medicare principles of cost reimbursement as modified by this Chapter and
using data provided by the Department.
(b) TEFRA limits. A hospitals Medicaid
allowable payment shall not exceed the TEFRA limits.
(c) Notice of Medicaid Program Reimbursement.
The Department shall, within sixty days after receipt of the Notice of Program
Reimbursement, send a Notice of Medicaid Program Reimbursement to the
hospital.
(d) Repayment of
overpayments. A hospital shall reimburse the Department for overpayments within
thirty days after the date of the Notice of Medicaid Program Reimbursement,
even if the provider has requested reconsideration or an administrative hearing
regarding the determination of overpayments. If a hospital does not timely
reimburse the Department, overpayments may be recovered pursuant to Section 14.
Notice of overpayments must include the hospitals right to request
reconsideration of the cost-settlement pursuant to Section 17. The
reconsideration shall be limited to whether the Department has complied with
the provisions of this rule.
(e)
Payment of underpayments. The Department shall request the issuance of payment
warrant to reimburse the hospital for underpayments within fifteen days after
the date of the Notice of Medicaid Program Reimbursement.