055-3 Wyo. Code R. §§ 3-35 - Production Test and Gas-Oil Ratio Report (Forms 10 through 13)
(a) Gas-oil ratio
reports can be required by the Supervisor on certain wells if it is deemed
necessary to obtain information of this nature.
(b) An initial gas well test can be required
by the Supervisor when such test is deemed necessary; the initial tests shall
be multipoint back-pressure tests (stabilized multipoint or constant time
multipoint or isochronal multipoint) or acceptable one-point back-pressure
tests. The results shall be furnished to the Supervisor on acceptable forms.
The methods prescribed in the Interstate Oil and Gas Compact Commission's
"Manual of Gas Well Testing" or an alternate method approved by the Supervisor
shall be used.
(c) As a guideline
for multipoint tests, each flow rate duration shall be set at a minimum of
thirty (30) minutes and a maximum of two (2) hours depending on stabilization.
The shut-in period shall be a minimum of seventy-two (72) hours.
(d) On one-point tests, the flow rate shall
be a minimum of twenty-four (24) hours, and the shut-in period shall be a
minimum of seventy-two (72) hours.
(e) Gas-oil ratio reports for horizontal
wells shall be filed upon initial completion and annually thereafter on Form
10.