055-4 Wyo. Code R. §§ 4-8 - Casing and Cementing of Injection Wells
(a) Wells used for
injection of gas, air, water, or other extraneous fluid into the producing
formation shall be cased with safe and adequate casing or tubing so as to
prevent leakage, and shall be so set or cemented that damage will not be caused
to oil, gas, or fresh water sources.
(b) The provisions of Chapter 3, Section 22
of these rules, shall apply to all injection wells.
(c) Before a new well drilled for injection
or disposal is operated, the casing outside the tubing shall be tested at the
greater of a minimum pressure of three hundred (300) psi or a pressure
equivalent to the maximum injection pressure, but no higher than one thousand
(1,000) psi. For the purpose of pressure testing, packers must be set within
one hundred feet (100') of perforations. The same rules apply to testing
existing wells newly converted to injection or disposal. Operators must provide
the Commission staff the opportunity to witness all integrity tests. In the
event a representative of the Commission is unable to witness the test, the
Operator is required to provide documentation of the test to the Commission. A
retrievable bridge plug will be utilized in casing to test tubingless
completions.