060-38 Wyo. Code R. §§ 38-10 - Ineligible Project Costs
The following costs are not eligible for funding under this program:
(a) Costs for preparation or
presentation of loan application;
(b) Costs incurred prior to loan award,
except costs incurred for architectural and engineering design, surveying and
environmental review, if required;
(c) Engineering fees, including design,
inspection and contract administration costs, in excess of fifteen percent
(15%) of project cost;
(d) Markups
by engineers/architects of sub-contractor and other outside charges;
(e) Costs for transportation, meals, lodging
and incidentals incurred offsite from the project or that exceed the current
federal per diem reimbursement rate;
(f) Costs associated with the borrower's own
employees and equipment;
(g) Costs
for real property in excess of current fair market value and/or costs for an
amount of real property in excess of that needed for project
purposes;
(h) Costs related to
issuance of bonds;
(i) Costs for
furnishings;
(j) Legal
fees;
(k) Costs for sidewalks that
are owned or maintained by a private property owner; and
(l) Costs for contingency or extra work
allowance in excess of 10% of estimated construction costs.