(a) In generalIn addition to the requirements for response plans for vessels established by section 1321(j) of this title, a response plan for a tanker loading cargo at a facility permitted under the Trans-Alaska Pipeline Authorization Act (43 U.S.C. 1651 et seq.), and a response plan for such a facility, shall provide for—
(1)
prepositioned oil spill containment and removal equipment in communities and other strategic locations within the geographic boundaries of Prince William Sound, including escort vessels with skimming capability; barges to receive recovered oil; heavy duty sea boom, pumping, transferring, and lightering equipment; and other appropriate removal equipment for the protection of the environment, including fish hatcheries;
(2)
the establishment of an oil spill removal organization at appropriate locations in Prince William Sound, consisting of trained personnel in sufficient numbers to immediately remove, to the maximum extent practicable, a worst case discharge or a discharge of 200,000 barrels of oil, whichever is greater;
(3)
training in oil removal techniques for local residents and individuals engaged in the cultivation or production of fish or fish products in Prince William Sound;
(b) DefinitionsIn this section—
(1)
the term “Prince William Sound” means all State and Federal waters within Prince William Sound, Alaska, including the approach to Hinchenbrook Entrance out to and encompassing Seal Rocks; and