The Secretary shall operate and maintain infrastructure and facilities to support the nuclear energy research, development, demonstration, and commercial application programs, including radiological facilities management, isotope production, and facilities management.
Not later than December 31, 2017, the Secretary shall provide for a versatile reactor-based fast neutron source, which shall operate as a national user facility.
In carrying out subparagraph (A), the Secretary shall consult with the private sector, institutions of higher education, the National Laboratories, and relevant Federal agencies to ensure that the user facility described in subparagraph (A) will meet the research needs of the largest practicable majority of prospective users.
As soon as practicable after determining the mission need under paragraph (1)(A), the Secretary shall submit to the appropriate committees of Congress a detailed plan for the establishment of the user facility.
The Secretary shall, to the maximum extent practicable, complete construction of, and approve the start of operations for, the user facility by not later than December 31, 2026.
The Secretary shall include in the annual budget request of the Department an explanation for any delay in the progress of the Department in completing the user facility by the deadline described in paragraph (4).
The Secretary shall leverage the best practices for management, construction, and operation of national user facilities from the Office of Science.