18 CFR Part 7 - PART 7—EXPEDITED LICENSING PROCESS FOR QUALIFYING NON-FEDERAL HYDROPOWER PROJECTS AT EXISTING NONPOWERED DAMS AND FOR CLOSED-LOOP PUMPED STORAGE PROJECTS
- § 7.1 Applicability and definitions.
- § 7.2 Use of expedited licensing process.
- § 7.3 Adequacy review of application.
- § 7.4 Additional information.
- § 7.5 Decision on request to use expedited licensing process.
- § 7.6 Notice of acceptance and ready for environmental analysis.
- § 7.7 Amendment of application.
- § 7.8 Other provisions.
- § 7.9 Transition provision.
Authority:
Source:
84 FR 17078, April 24, 2019, unless otherwise noted.