30 CFR 250.1151 - How often must I conduct well production tests?

prev | next
§ 250.1151 How often must I conduct well production tests?
(a) You must conduct well production tests as shown in the following table:
You must conduct: And you must submit to the Regional Supervisor:
(1) A well-flow potential test on all new, recompleted, or reworked well completions within 30 days of the date of first continuous production, Form BSEE-0126, Well Potential Test Report, along with the supporting data as listed in the table in § 250.1167, within 15 days after the end of the test period.
(2) At least one well test during a calendar half-year for each producing completion, Results on Form BSEE-0128, Semiannual Well Test Report, of the most recent well test obtained. This must be submitted within 45 days after the end of the calendar half-year.
(b) You may request an extension from the Regional Supervisor if you cannot submit the results of a semiannual well test within the specified time.
(c) You must submit to the Regional Supervisor an original and two copies of the appropriate form required by paragraph (a) of this section; one of the copies of the form must be a public information copy in accordance with §§ 250.186 and 250.197, and marked “Public Information.” You must submit two copies of the supporting information as listed in the table in § 250.1167 with form BSEE-0126.

Title 30 published on 2014-07-01

no entries appear in the Federal Register after this date.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 30 - MINERAL LANDS AND MINING
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR 250 after this date.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9916 - Oil and Gas and Sulphur Operations on the Outer Continental Shelf—Requirements for Exploratory Drilling on the Arctic Outer Continental Shelf
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Ocean Energy Management, Bureau of Safety and Environmental Enforcement
      Proposed rule.
      Submit comments by April 27, 2015. BOEM and BSEE may not fully consider comments received after this date. You may submit comments to the Office of Management and Budget (OMB) on the information collection burden in this proposed rule by March 26, 2015. The deadline for comments on the information collection burden does not affect the deadline for the public to comment to BOEM and BSEE on the proposed regulations.
      30 CFR Parts 250 and 254