30 CFR 250.920 - What are the BSEE requirements for assessment of fixed platforms?

Beta! The text on the eCFR tab represents the unofficial eCFR text at ecfr.gov.
§ 250.920 What are the BSEE requirements for assessment of fixed platforms?
Link to an amendment published at 81 FR 36150, June 6, 2016.

(a) You must document all wells, equipment, and pipelines supported by the platform if you intend to use either the A-2 or A-3 assessment category. Assessment categories are defined in API RP 2A-WSD, Section 17.3 (as incorporated by reference in § 250.198). If BSEE objects to the assessment category you used for your assessment, you may need to redesign and/or modify the platform to adequately demonstrate that the platform is able to withstand the environmental loadings for the appropriate assessment category.

(b) You must perform an analysis check when your platform will have additional personnel, additional topside facilities, increased environmental or operational loading, or inadequate deck height your platform suffered significant damage (e.g., experienced damage to primary structural members or conductor guide trays or global structural integrity is adversely affected); or the exposure category changes to a more restrictive level (see Sections 17.2.1 through 17.2.5 of API RP 2A-WSD, incorporated by reference in § 250.198, for a description of assessment initiators).

(c) You must initiate mitigation actions for platforms that do not pass the assessment process of API RP 2A-WSD. You must submit applications for your mitigation actions (e.g., repair, modification, decommissioning) to the Regional Supervisor for approval before you conduct the work.

(d) The BSEE may require you to conduct a platform design basis check when the reduced environmental loading criteria contained in API RP 2A-WSD Section 17.6 are not applicable.

(e) By November 1, 2009, you must submit a complete list of all the platforms you operate, together with all the appropriate data to support the assessment category you assign to each platform and the platform assessment initiators (as defined in API RP 2A-WSD) to the Regional Supervisor. You must submit subsequent complete lists and the appropriate data to support the consequence-of-failure category every 5 years thereafter, or as directed by the Regional Supervisor.

(f) The use of Section 17, Assessment of Existing Platforms, of API RP 2A-WSD is limited to existing fixed structures that are serving their original approved purpose. You must obtain approval from the Regional Supervisor for any change in purpose of the platform, following the provisions of API RP 2A-WSD, Section 15, Re-use.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.

United States Code
U.S. Code: Title 31 - MONEY AND FINANCE
U.S. Code: Title 43 - PUBLIC LANDS

Title 30 published on 2015-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 30 CFR Part 250 after this date.

  • 2015-12-04; vol. 80 # 233 - Friday, December 4, 2015
    1. 80 FR 75806 - Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Decommissioning Costs
      GPO FDSys XML | Text
      DEPARTMENT OF THE INTERIOR, Bureau of Safety and Environmental Enforcement
      Final rule.
      This final rule becomes effective on January 4, 2016.
      30 CFR Part 250