§ 61.44 Stack sampling.

(a) Sources subject to § 61.42(b) shall be continuously sampled, during release of combustion products from the tank, according to Method 104 of appendix B to this part. Method 103 of appendix B to this part is approved by the Administrator as an alternative method for sources subject to § 61.42(b).

(b) All samples shall be analyzed, and beryllium emissions shall be determined within 30 days after samples are taken and before any subsequent rocket motor firing or propellant disposal at the given site. All determinations shall be reported to the Administrator by a registered letter dispatched before the close of the next business day following such determinations.

(c) Records of emission test results and other data needed to determine total emissions shall be retained at the source and made available, for inspection by the Administrator, for a minimum of 2 years.

(d) The Administrator shall be notified at least 30 days prior to an emission test, so that he may at his option observe the test.

[ 38 FR 8826, Apr. 6, 1973, as amended at 50 FR 46294, Nov. 7, 1985]

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code
U.S. Code: Title 42 - THE PUBLIC HEALTH AND WELFARE

Title 40 published on 2015-08-22

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR Part 61 after this date.

  • 2017-01-26; vol. 82 # 16 - Thursday, January 26, 2017
    1. 82 FR 8499 - Delay of Effective Date for 30 Final Regulations Published by the Environmental Protection Agency Between October 28, 2016 and January 17, 2017
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Final rule; delay of effective dates.
      This regulation is effective January 26, 2017. The effective date of each regulation listed in the table below is delayed to a new effective date of March 21, 2017.
      40 CFR Parts 22, 51, 52, 61, 68, 80, 81, 124, 147, 171, 239, 259, 300, and 770