40 CFR 63.11089 - What requirements must I meet for equipment leak inspections if my facility is a bulk gasoline terminal, bulk plant, pipeline breakout station, or pipeline pumping station?

Status message

There are 12 Updates appearing in the Federal Register for 40 CFR 63. View below or at eCFR (GPOAccess)
prev | next
§ 63.11089 What requirements must I meet for equipment leak inspections if my facility is a bulk gasoline terminal, bulk plant, pipeline breakout station, or pipeline pumping station?
(a) Each owner or operator of a bulk gasoline terminal, bulk plant, pipeline breakout station, or pipeline pumping station subject to the provisions of this subpart shall perform a monthly leak inspection of all equipment in gasoline service, as defined in § 63.11100. For this inspection, detection methods incorporating sight, sound, and smell are acceptable.
(b) A log book shall be used and shall be signed by the owner or operator at the completion of each inspection. A section of the log book shall contain a list, summary description, or diagram(s) showing the location of all equipment in gasoline service at the facility.
(c) Each detection of a liquid or vapor leak shall be recorded in the log book. When a leak is detected, an initial attempt at repair shall be made as soon as practicable, but no later than 5 calendar days after the leak is detected. Repair or replacement of leaking equipment shall be completed within 15 calendar days after detection of each leak, except as provided in paragraph (d) of this section.
(d) Delay of repair of leaking equipment will be allowed if the repair is not feasible within 15 days. The owner or operator shall provide in the semiannual report specified in § 63.11095(b), the reason(s) why the repair was not feasible and the date each repair was completed.
(e) You must comply with the requirements of this subpart by the applicable dates specified in § 63.11083.
(f) You must submit the applicable notifications as required under § 63.11093.
(g) You must keep records and submit reports as specified in §§ 63.11094 and 63.11095.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63