§ 63.7945 What are my monitoring installation, operation, and maintenance requirements?
(a) Each CPMS must meet the requirements in paragraphs (a)(1) through (4) of this section.
(1) Complete a minimum of one cycle of operation for each successive 15-minute period.
(2) To calculate a valid hourly value, you must have at least three of four equally spaced data values (or at least two, if that condition is included to allow for periodic calibration checks) for that hour from a CPMS that is not out of control according to the monitoring plan referenced in § 63.7935.
(3) To calculate the average emissions for each averaging period, you must have at least 75 percent of the hourly averages for that period using only block hourly average values that are based on valid data (i.e., not from out-of-control periods).
(4) Unless otherwise specified, each CPMS must determine the hourly average of all recorded readings and daily average, if required.
(b) You must record the results of each inspection, calibration, and validation check.
(c) You must conduct a performance evaluation for each CPMS according to the requirements in § 63.8(e) and your site-specific monitoring plan.

Title 40 published on 2014-07-01

The following are only the Rules published in the Federal Register after the published date of Title 40.

For a complete list of all Rules, Proposed Rules, and Notices view the Rulemaking tab.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code

Title 40 published on 2014-07-01

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 40 CFR 63 after this date.

  • 2015-02-24; vol. 80 # 36 - Tuesday, February 24, 2015
    1. 80 FR 9613 - New Source Performance Standards and National Emission Standards for Hazardous Air Pollutants; Delegation of Authority to Louisiana
      GPO FDSys XML | Text
      ENVIRONMENTAL PROTECTION AGENCY
      Direct final rule; delegation of authority.
      This rule is effective on April 27, 2015 without further notice, unless EPA receives relevant adverse comment by March 26, 2015. If EPA receives such comment, EPA will publish a timely withdrawal in the Federal Register informing the public that the updated NESHAPs delegation will not take effect; however, the NSPS delegation will not be affected by such action.
      40 CFR Parts 60, 61, and 63