40 CFR Appendix Table 1 to Subpart VVVV of Part 63, Compliance Dates for New and Existing Boat Manufacturing Facilities

Table 1 to Subpart VVVV of Part 63 - Compliance Dates for New and Existing Boat Manufacturing Facilities

As specified in § 63.5695, you must comply by the dates in the following table:

If your facility is - And - Then you must comply by this date -
1. An existing source Is a major source on or before August 22, 2001 1 August 23, 2004.
2. An existing or new area source Becomes a major source after August 22, 2001 1 1 year after becoming a major source or August 22, 2002, whichever is later.
3. A new source Is a major source at startup 1 Upon startup or August 22, 2001, whichever is later.

1Your facility is a major source if it is a stationary source or group of stationary sources located within a contiguous area and under common control that emits or can potentially emit, considering controls, in the aggregate, 9.1 megagrams or more per year of a single hazardous air pollutant or 22.7 megagrams or more per year of a combination of hazardous air pollutants.

This is a list of United States Code sections, Statutes at Large, Public Laws, and Presidential Documents, which provide rulemaking authority for this CFR Part.

This list is taken from the Parallel Table of Authorities and Rules provided by GPO [Government Printing Office].

It is not guaranteed to be accurate or up-to-date, though we do refresh the database weekly. More limitations on accuracy are described at the GPO site.


United States Code