40 CFR Appendix Table 1 to Subpart WWWW of Part 60 - Model Rule—Compliance Schedules and Increments of Progress
Table 1 to Subpart WWWW of Part 60—Model Rule—Compliance Schedules and Increments of Progress
| Affected units | Increment 1
(submit final control plan) |
Increment 2
(award contracts) |
Increment 3
(begin onsite construction) |
Increment 4
(complete onsite construction) |
Increment 5
(final compliance) |
|---|---|---|---|---|---|
| 1. All municipal waste combustors. a | (Dates to be specified in state plan) | (Dates to be specified in state plan) | (Dates to be specified in state plan) | (Dates to be specified in state plan) | (Dates to be specified in state plan). b |
a Plant specific schedules can be used at the discretion of the state.
b The date can be no later than 3 years after the effective date of state plan approval or March 10, 2031.