§ 1.1410 Remedies.

If the Commission determines that the rate, term, or condition complained of is not just and reasonable, it may prescribe a just and reasonable rate, term, or condition and may:

(a) If the Commission determines that the rate, term, or condition complained of is not just and reasonable, it may prescribe a just and reasonable rate, term, or condition and may:

(1) Terminate the unjust and/or unreasonable rate, term, or condition;

(2) Substitute in the pole attachment agreement the just and reasonable rate, term, or condition established by the Commission;

(3) Order a refund, or payment, if appropriate. The refund or payment will normally be the difference between the amount paid under the unjust and/or unreasonable rate, term, or condition and the amount that would have been paid under the rate, term, or condition established by the Commission, plus interest, consistent with the applicable statute of limitations; and

(b) If the Commission determines that access to a pole, duct, conduit, or right-of-way has been unlawfully denied or delayed, it may order that access be permitted within a specified time frame and in accordance with specified rates, terms, and conditions.

(c) Order a refund, or payment, if appropriate. The refund or payment will normally be the difference between the amount paid under the unjust and/or unreasonable rate, term, or condition and the amount that would have been paid under the rate, term, or condition established by the Commission from the date that the complaint, as acceptable, was filed, plus interest.

[ 44 FR 31650, June 1, 1979, as amended at 76 FR 26639, May 9, 2011]

Title 47 published on 09-May-2017 04:29

The following are ALL rules, proposed rules, and notices (chronologically) published in the Federal Register relating to 47 CFR Part 1 after this date.

  • 2017-05-18; vol. 82 # 95 - Thursday, May 18, 2017
    1. 82 FR 22742 - Promoting Technological Solutions To Combat Contraband Wireless Device Use in Correctional Facilities
      GPO FDSys XML | Text
      FEDERAL COMMUNICATIONS COMMISSION
      Final rule.
      Effective June 19, 2017, with the exception of: (1) §§ 1.9020(d)(8), 1.9030(d)(8), 1.9035(d)(4), and 20.18(a), which contain information collection requirements that require approval by the Office of Management and Budget (OMB), and which the Commission will announce by publishing a document in the Federal Register ; and (2) §§ 1.9020(n), 1.9030(m), 1.9035(o), 20.18(r), and 20.23(a), which require approval by OMB under the Paperwork Reduction Act (PRA), and which the Commission will announce by publishing a document in the Federal Register .