11 AAC 87.070 - Drilling permit
(a) Unless authorized under
11 AAC 87.030, a drilling permit
is required before the drilling, redrilling, or deepening of any well and
before the reentry of an abandoned well. However, in an emergency, oral
approval by the commissioner of any operation covered by
11 AAC 87.070 -
11 AAC 87.190 is
sufficient.
(b) The application fee
prescribed by
11 AAC 05.140 must accompany each
application for a drilling permit. The application must include the following:
(1) the name and address of the landowner or
lessee;
(2) a legal description and
map of the parcel and well location;
(3) the name and address of the
operator;
(4) the well name and
number;
(5) the proposed
bottom-hole coordinates for a directionally drilled well;
(6) the datum elevation or elevation of the
derrick floor, rotary table, or kelly bushing, relative to surface
level;
(7) the elevation of the
ground, relative to sea level;
(8)
the estimated depth of the intended zone of completion, relative to
datum;
(9) the estimated planned
total depth, relative to datum;
(10) a description of the proposed casing
program as required in
11 AAC 87.120;
(11) a description of the blowout prevention
equipment to be used and the information required by
11 AAC 87.130;
(12) a description of the proposed sump plan
and method of sump abandonment;
(13) an indemnity bond as required by
11 AAC 87.080; and
(14) any other relevant information the
commissioner determines necessary.
(c) For a well which is to be intentionally
deviated, the application for the drilling permit must also include
(1) the surface and proposed producing
interval locations;
(2) a plat
drawn to an appropriate scale showing the path of the proposed wellbore in
relation to all other vertical and deviated wellbores which are within a
distance of 2000 feet from the proposed wellbore; the true vertical depths must
be shown at frequent intervals along each wellbore; and
(3) a neat and accurate plat of the lease and
all affected leases, showing the names of all affected owners and the surface
and proposed producing interval locations of the well and all other wells
within one-half mile of any portion of the new well; the plat must be drawn to
a scale which will permit easy observation of all pertinent data.
(d) If drilling is not commenced
within 24 months after approval, the drilling permit expires.
(e) Any proposed changes to the drilling
permit must be approved by the commissioner.
Notes
Authority:AS 38.05.035
AS 41.06.020
AS 41.06.040
AS 41.06.050