18 AAC 72.660 - After-the-fact registration
If an alternative onsite wastewater system not requiring plan approval was not registered in accordance with 18 AAC 72.650(c), a registered engineer may submit for the department's assessment an after-the-fact registration, or otherwise document a changed use or condition by
(1) submitting the registration fee
required under
18 AAC 72.955;
(2) submitting an adequacy report that is
sealed by the registered engineer responsible for performing the evaluation;
the adequacy report must include
(A) a
description of the facility served including calculations for total design
flow;
(B) a description of the
methods and procedures used to verify that the system conforms to the
requirements of
18 AAC 72.601 -
18 AAC 72.660, and the ability of
the system to accept the hydraulic and organic loads from the facility it
serves;
(C) information, as can be
fairly determined or reasonably assumed, regarding
(i) the size, material, and functionality of
all treatment components;
(ii) the
assessment of the final disposal area; and
(iii) site-specific conditions, including a
classification of soils typically encountered in the area or a test hole log
verifying soil conditions, the depth to groundwater table, and the general
topography of the area;
(D) results of laboratory analysis for
samples collected from various stages of treatment, as applicable, to
demonstrate system performance; and
(E) a site plan drawn to a standard
engineering scale, showing the developed features on the lot, the onsite
wastewater system location based on visible features such as cleanouts and
monitor tubes, the likely locations of subsurface components, and all nearby
public and private water sources and surface water; and
(3) submitting a request for a waiver in
accordance with
18 AAC 72.640 if the system does
not meet the construction requirements of
18 AAC 72.630 or the separation
distance requirements listed in
18 AAC
72.620.
Notes
Authority:AS 44.46.020
AS 46.46.025
AS 46.03.020
AS 46.03.050
AS 46.03.100
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.