Ariz. Admin. Code § R14-2-2601 - Definitions
In this Article, unless otherwise specified:
1. "AC" means alternating current.
2. "Applicant" means a Customer or
Representative who submits an Interconnection Application pursuant to this
Article.
3. "Application" means the
standard form or format for an Applicant to apply to a Utility for
Interconnection of a Generating Facility with the Distribution
System.
4. "Backfeed" means to
energize a section of a Utility electric system with a Generating
Facility.
5. "Calendar Day" means
any day including Saturday, Sunday, or a Federal or State Holiday.
6. "Certified Equipment" means a specific
generating and protective equipment system or systems certified as meeting the
requirements in R14-2-2611 relating to testing, operation, safety, and
reliability by an NRTL.
7.
"Clearance" means documentation from a Utility stating that a line or equipment
is disconnected from all known sources of power and tagged; that for safety
purposes all proper precautionary measures have been taken; and that workers
may proceed to inspect, test, and install ground on the circuit.
8. "CFR" means Code of Federal
Regulations.
9. "Commission" means
the Arizona Corporation Commission.
10. "Customer" means an electric consumer
applying to connect a Generating Facility on the consumer's side of the Utility
meter, whether an Exporting System, a Non-Exporting System, or an Inadvertent
Export System.
11. "DC" means
direct current.
12. "Disconnect
Switch" means a device that:
a. Is installed
and maintained for a Generating Facility by the Customer;
b. Is a visible-open, manual, gang-operated,
load break disconnect device;
c. Is
capable of being locked in a visible-open position by a standard Utility
padlock that will completely isolate the Generating Facility from the
Distribution System; and
d. If the
voltage of the Generating Facility is over 500 volts, is capable of being
grounded on the Utility side.
13. "Distributed Generation" means any type
of Customer electrical generator, solid-state or static inverter, or Generating
Facility interconnected with the Distribution System that either can be
operated in electrical parallel with the Distribution System or can feed a
Customer load that can also be fed by the Distribution System.
14. "Distribution System" means the
infrastructure constructed, maintained, and operated by a Utility to deliver
electric service at the distribution level (69 kV or less) to retail
consumers.
15. "Electric
Cooperative" means a Utility that is:
a. Not
operated for profit;
b. Owned and
controlled by its members; and
c.
Operating as a public service company in this state.
16. "Exporting System" means any type of
Generating Facility that is designed to regularly Backfeed the Distribution
System.
17. "Facilities Study"
means a comprehensive analysis of the actual construction needed to take place
based on the outcome of a System Impact Study.
18. "Fault Current" means the level of
current that can flow if a short circuit is applied to a voltage
source.
19. "Feasibility Study"
means a preliminary review of the potential impacts on the Distribution System
that will result from a proposed Interconnection.
20. "Generating Facility" means all or part
of a Customer's electrical generator(s), energy storage system(s), or any
combination of electrical generator(s) and storage system(s), together with all
inverter(s) and protective, safety, and associated equipment necessary to
produce electric power at the Customer's facility; this includes solid-state or
static inverters, induction machines, and synchronous machines.
21. "Good Utility Practice" means any of the
practices, methods, and acts engaged in or approved by a significant portion of
the electric industry during the relevant time period, or any of the practices,
methods, and acts that, in the exercise of reasonable judgment in light of the
facts known at the time the decision was made, could have been expected to
accomplish the desired result at a reasonable cost consistent with reliability,
safety, and expedition. Good Utility Practice is not intended to be limited to
the optimal practice, method, or act to the exclusion of all others, but rather
to include practices, methods, or acts generally accepted in the region at the
relevant time.
22. "IEEE" means the
Institute of Electrical and Electronics Engineers, Inc.
23. "Inadvertent Export" means the unplanned,
uncompensated transfer of electrical energy from a Generating Facility to the
Distribution System across the Point of Interconnection.
24. "Interconnection" means the physical
connection of a Generating Facility to the Distribution System.
25. "Interconnection Agreement" means an
agreement, signed between the Utility and the Customer, covering the terms and
conditions governing the Interconnection and operation of the Generating
Facility with the Utility, and includes any appendices to the
agreement.
26. "Interconnection
Facilities" means the electrical wires, switches, and related equipment that
are required, in addition to the facilities required to provide electric
distribution service to a Customer, to allow Interconnection. Interconnection
Facilities may be located on either side of the Point of Interconnection as
appropriate to their purpose and design.
27. "Interconnection Manual" means a separate
document developed and maintained by a Utility as required under
R14-2-2628.
28. "Interconnection
Study" means a study that may be undertaken by a Utility (or a
Utility-designated third party) in response to the Utility's receipt of a
completed Application. An Interconnection Study may include:
a. A Feasibility Study;
b. A System Impact Study;
c. A Facilities Study; and
d. Any additional analysis required by the
Utility.
29. "Islanding"
means a condition in which a portion of the Distribution System is energized
solely by one or more local electric power systems throughout the associated
Point of Interconnection while that portion of the Distribution System is
electrically separated from the rest of the Distribution System. Islanding can
be either intentional (planned) or unintentional (unplanned).
30. "Jurisdictional Electric Inspection
Agency" means the governmental authority having jurisdiction to inspect and
approve the installation of a Generating Facility.
31. "kW" means kilowatt.
32. "Maximum Capacity" means:
a. The nameplate AC capacity of a Generating
Facility; or
b. If the Operating
Characteristics of the Generating Facility limit the power transferred across
the Point of Interconnection to the Distribution System, only the power
transferred across the Point of Interconnection to the Distribution System, not
including Inadvertent Export.
33. "MW" means megawatt.
34. "Non-Exporting System" means a system in
which there is no designed, regular export of power from the Generating
Facility to the Distribution System.
35. "NRTL" means a Nationally Recognized
Testing Laboratory recognized by the U.S. Occupational Safety and Health
Administration.
36. "Operating
Characteristics" means the mode of operation of a Generating Facility
(Exporting System, Non-Exporting System, or Inadvertent Exporting System) that
controls the amount of power delivered across the Point of Interconnection to
the Distribution System.
37.
"Parallel Operation" means the operation of a Generating Facility that is
electrically interconnected to a bus common with the Distribution System,
either on a momentary or continuous basis.
38. "Protective Functions" means the
equipment, hardware, or software in a Generating Facility that protects against
Unsafe Operating Conditions.
39.
"Point of Interconnection" means the physical location where the Utility's
service conductors are connected to the Customer's service conductors to allow
Parallel Operation of the Generating Facility with the Distribution
System.
40. "Relay" means an
electric device that is designed to interpret input conditions in a prescribed
manner and, after specified conditions are met, to respond and cause contact
operation or similar abrupt change in associated electric control
circuits.
41. "Representative"
means an agent of the Customer who is designated by the Customer and is acting
on the Customer's behalf.
42. "RUS"
means the U.S. Department of Agriculture Rural Utilities Service.
43. "Scoping Meeting" means an initial review
meeting between a Utility and a Customer or Representative during which a
general overview of the proposed Generating Facility design is discussed, and
the Utility provides general information on system conditions at the proposed
Point of Interconnection.
44.
"Secondary Spot Network System" means an AC power Distribution System meeting
the criteria in R14-2-2622.
45.
"System Impact Study" means a full engineering review of the impact on the
Distribution System from a Generating Facility, including power flow, Utility
system protective device coordination, generator protection schemes (if not
Certified Equipment), stability, voltage fluctuations, frequency impacts, and
short circuit study. A System Impact Study may consider total nameplate
capacity of the Generating Facility.
46. "UL 1741" means the Underwriters
Laboratories Inc. Standard for Inverters, Converters, Controllers and
Interconnection System Equipment for Use with Distributed Energy Resources
(February 15, 2018), with no future editions or amendments, which is
incorporated by reference; on file with the Commission; and published by and
available from Underwriters Laboratories Inc., 151 Eastern Avenue Bensenville,
IL 60106-3072 and through https://standardscatalog.ul.com.
47. "UL 1741SA" means the approved
supplemental amendment of UL 1741 that defines the manufacturing (including
software) and product testing requirements for advanced inverters.
48. "Unsafe Operating Conditions" means
conditions that, if left uncorrected, could result in any of the following:
a. Harm to personnel;
b. Damage to equipment;
c. An adverse effect to the safe operation of
the Distribution System; or
d.
Operation of the Generating Facility outside pre-established parameters
required by the Interconnection Agreement.
49. "Utility" means an electric distribution
company that constructs, operates, and maintains its Distribution System for
the receipt and delivery of electricity and that is a public service
corporation under Arizona Constitution, Article 15, § 2.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.