Ariz. Admin. Code § R14-2-2614 - Application and Generating Facility General Requirements
A. A Customer desiring to interconnect to the
Distribution System a Generating Facility that is not a Non-Exporting
inverter-based energy storage Generating Facility or an Inadvertent Export
Generating Facility with a Maximum Capacity of 20 kW or less shall apply to the
Utility for Interconnection as provided in this Section.
B. An Applicant shall submit an Application
on a form provided by the Utility, or according to a format provided by the
Utility, along with the following:
1. All
supplemental information and documents required by the Utility, which shall be
noted on the Utility's Application or Application instructions;
2. An executed Interconnection Agreement, if
required by the Utility; and
3. An
initial Application or processing fee, if a tariff containing such a fee is
approved for the Utility by the Commission.
C. Upon request, a Utility shall provide an
Applicant with sample diagrams that indicate the preferred level of detail and
type of information required for a typical inverter-based system.
D. Within seven calendar days after receiving
an Application, a Utility shall review the Application and provide the
Applicant notice:
1. That the Application
satisfies all requirements under subsection (B); or
2. That the Application does not satisfy one
or more requirements under subsection (B), in which case:
a. The Utility shall specify the additional
information or documents required;
b. The Applicant shall submit the specified
information or documents; and
c.
The Application may be deemed withdrawn if the Applicant does not submit the
required information or documents within 30 calendar days.
E. A Generating Facility shall
comply with the following general requirements:
1. If inverter based, each inverter shall
meet the shutdown protective functions (under/over voltage, under/over
frequency, and anti-Islanding) specified in IEEE 1547-2018 - IEEE Standard for
Interconnection and Interoperability of Distributed Energy Resources with
Associated Electric Power Systems Interfaces (April 6, 2018), with no future
editions or amendments, which is incorporated by reference; on file with the
Commission; and published by and available from IEEE, 3 Park Avenue, 17th
Floor, New York, New York 10016, and through
http://ieeexplore.ieee.org;
2. The Generating Facility shall meet all
applicable codes and standards required by this Article and referenced in the
Utility Interconnection Manual; and
3. The Generating Facility shall comply with
the Utility's Interconnection Manual and Interconnection Agreement
requirements.