Ariz. Admin. Code § R18-12-219 - Installation of New UST Systems
A.
An owner or operator that intends to bring a new underground storage tank
system into operation shall submit to the Director on a Department form all of
the following information at least 30 days before beginning installation:
1. The tank's size, construction material,
manufacturer, and intended system contents;
2. The certified UST service provider who
will perform or supervise the installation;
3. Detailed installation plans showing the
site drawn to scale, piping layouts, electrical service, and stating that the
tanks will be installed according to the manufacturer's instructions, and the
applicable installation standards and codes of practice in
R18-12-220 and
R18-12-281;
4. Evidence that the intended system contents
are compatible with the UST system;
5. A statement describing how the owner or
operator plans to satisfy financial responsibility in accordance with Article
3;
6. The intended installation
schedule with the proposed backfill date.
B. Within 15 calendar days of receipt of the
information required in subsection (A), the Department shall send the owner or
operator an email indicating whether the proposed installation may or may not
proceed, or whether further information is necessary.
C. An owner or operator may not backfill a
new tank system installation until approval by a representative of the Director
after an onsite inspection. At the time of inspection the owner or operator
shall have on site certifications for all equipment and test results for all
piping.