Ariz. Admin. Code § R18-9-D904 - AZPDES Permit Coverage Deadlines
A. Any person who owns or operates a CAFO
shall apply for or seek coverage under an AZPDES permit and shall comply with
all applicable AZPDES requirements, including the duty to maintain permit
coverage under subsection (C).
1. Permit
coverage deadline for an animal feeding operation operating before April 14,
2003.
a. An owner or operator of an animal
feeding operation that operated before April 14, 2003 and was defined as a CAFO
before February 2, 2004 shall apply for or seek permit coverage or maintain
permit coverage and comply with the conditions of the applicable AZPDES
permit;
b. An owner or operator of
an animal feeding operation that operated before April 14, 2003 and was not
defined as a CAFO until February 2, 2004 shall apply for or seek permit
coverage by a date specified by the Director, but no later than February 13,
2006;
c. An owner or operator of an
animal feeding operation that operated before April 14, 2003 who changes the
operation on or after February 2, 2004, resulting in the operation being
defined as a CAFO, shall apply for or seek permit coverage as soon as possible,
but no later than 90 days after the operational change. If the operational
change will not make the operation a CAFO as defined before February 2, 2004,
the owner or operator may take until April 13, 2006 or 90 days after the
operation is defined as a CAFO, whichever is later, to apply for or seek permit
coverage;
d. An owner or operator
of an animal feeding operation that operated before April 14, 2003 who
constructs additional facilities on or after February 2, 2004, resulting in the
operation being defined as a CAFO that is a new source, shall apply for or seek
permit coverage at least 180 days before the new source portion of the CAFO
commences operation. If the calculated 180-day deadline occurs before February
2, 2004 and the operation is not subject to this Article before February 2,
2004, the owner or operator shall apply for or seek permit coverage no later
than March 3, 2004.
2.
Permit coverage deadline for an animal feeding operation operating on or after
April 14, 2003. An owner or operator who started construction of a CAFO on or
after April 14, 2003, including a CAFO subject to the effluent limitations
guidelines in 40 CFR 412, shall apply for or seek permit coverage at least 180
days before the CAFO commences operation. If the calculated 180-day deadline
occurs before February 2, 2004 and the operation is not subject to this Article
before February 2, 2004, the owner or operator shall apply for or seek permit
coverage no later than March 3, 2004.
3. Permit coverage deadline for a designated
CAFO. Any person who owns or operates a CAFO designated under
R18-9-D901(B)
shall apply for or seek permit coverage no later than 90 days after receiving a
designation notice.
B.
Unless specified under
R18-9-D903(E) and
(F), the Director shall not require permit
coverage for a CAFO that the Director determines under
R18-9-D903 to have no potential to
discharge. If circumstances change at a CAFO that has a no potential to
discharge determination and the CAFO now has a potential to discharge, the
person who owns or operates the CAFO shall notify the Director within 30 days
after the change in circumstances and apply for or seek coverage under an
AZPDES permit.
C. Duty to maintain
permit coverage.
1. The permittee shall:
a. If covered by an individual AZPDES permit,
submit an application to renew the permit no later than 180 days before the
expiration of the permit under
R18-9-B904(B);
or
b. If covered by a general
AZPDES permit, comply with
R18-9-C903(B).
2. Continued permit coverage or
reapplication for a permit is not required if:
a. The facility ceases operation or is no
longer a CAFO; and
b. The permittee
demonstrates to the Director that there is no potential for a discharge of
remaining manure, litter, or associated process wastewater (other than
agricultural stormwater from land application areas) that was generated while
the operation was a CAFO.