Design and
installation requirements.
1. General
provisions. In addition to the applicable requirements in
R18-9-A312, the applicant shall:
a. Ensure that the septic tank meets the
requirements specified in
R18-9-A314;
b. Before placing aggregate or disposal pipe
in a prepared excavation, remove all smeared or compacted surfaces from
trenches by raking to a depth of 1 inch and removing loose material. The
applicant shall:
i. Place aggregate in the
trench to the depth and grade specified in subsection (C)(2);
ii. Place the drain pipe on aggregate and
cover it with aggregate to the minimum depth specified in subsection (C)(2);
and
iii. Cover the aggregate with
landscape filter material, geotextile, or similar porous material to prevent
filling of voids with earth backfill;
c. Use a grade board stake placed in the
trench to the depth of the aggregate if the disposal pipe is constructed of
drain tile or flexible pipe that will not maintain alignment without continuous
support;
d. Disposal pipe. If two
or more disposal pipes are installed, install a distribution box approved by
the Department of sufficient size to receive all lateral lines and flows at the
head of each disposal works and:
i. Ensure
that the inverts of all outlets are level and the invert of the inlet is at
least 1 inch above the outlets;
ii.
Design distribution boxes to ensure equal flow and install the boxes on a
stable level surface such as a concrete slab or native or compacted soil;
and
iii. Protect concrete
distribution boxes from corrosion by coating them with an appropriate
bituminous coating, constructing the boxes with concrete that has a 15 to 18
percent fly ash content, or by using other equivalent
means;
e. Construct all
lateral pipes running from a distribution box to the disposal works with
watertight joints and ensure that multiple disposal laterals, wherever
practical, are of uniform length;
f. Lay pipe connections between the septic
tank and a distribution box on natural ground or compact fill and construct the
pipe connections with watertight joints;
g. Construct steps within distribution line
trenches or beds, if necessary, to maintain a level disposal pipe on sloping
ground. The applicant shall construct the lines between each horizontal section
with watertight joints and install them on natural or unfilled ground; and
h. Ensure that a disposal works
consisting of trenches, beds, chamber technology, or seepage pits is not paved
over or covered by concrete or any material that can reduce or inhibit possible
evaporation of wastewater through the soil to the land surface or oxygen
transport to the soil absorption surfaces.
2. Trenches.
a. The applicant shall calculate the trench
absorption area as the total of the trench bottom area and the sum of both
trench sidewall areas to a maximum depth of 48 inches below the bottom of the
disposal pipe.
b. The applicant
shall ensure that trench bottoms and disposal pipe are level. The applicant
shall calculate trench sizing from the soil absorption rate specified under
R18-9-A312(D)
and the design flow established in
R18-9-A312(B).
c. The following design criteria for trenches
apply:
|
Trenches
|
Minimum
|
Maximum
|
|
1. Number of trenches
|
1 (2 are recommended)
|
No Maximum
|
|
2. Length of
trench1
|
----
|
100 feet
|
|
3. Bottom width of trench
|
12 inches
|
36 inches
|
|
4. Trench absorption area (sq. ft. of absorption
area per linear foot of trench)
|
No Minimum
|
11 sq. ft.
|
|
5. Depth of cover over aggregate surrounding
disposal pipe
|
9 inches
|
24 inches2
|
|
6. Thickness of aggregate material over disposal
pipe
|
2 inches
|
2 inches
|
|
7. Thickness of aggregate material under disposal
pipe
|
12 inches
|
No Maximum
|
|
8. Slope of disposal pipe
|
Level
|
Level
|
|
9. Disposal pipe diameter
|
3 inches
|
4 inches
|
|
10. Spacing of trenches (measured between nearest
side-walls)
|
2 times effective depth3
or five feet, whichever is greater
|
No Maximum
|
|
Notes:
1. If unequal trench lengths are used, proportional
distribution of waste-water is required.
2. For more than 24 inches, Standard Dimensional
Ratio 35 or equivalent strength pipe is required.
3. The effective depth is the distance between the
bottom of the disposal pipe and the bottom of the trench bed.
|
d.
The applicant may substitute clean, durable, crushed, and washed recycled
concrete for aggregate if noted in design documents and the trench absorption
area calculation excludes the trench bottom.
3. Beds. An applicant shall:
a. If a bed is installed, use the soil
absorption rate specified in
R18-9-A312(D)
for "SAR, Bed. The applicant may, in computing the bed bottom absorption area,
include the bed bottom and the perimeter side-wall area not more than 36 inches
below the disposal pipe;
b. Comply
with the following design criteria for beds:
|
Gravity Beds
|
Minimum
|
Maximum
|
|
1. Number of disposal pipes
|
2
|
No Maximum
|
|
2. Length of bed
|
No Minimum
|
100 feet
|
|
3. Distance between disposal pipes
|
4 feet
|
6 feet
|
|
4. Spacing of beds measured between nearest
sidewalls
|
2 times effective depth1
or 5 feet, whichever is greater
|
No Maximum
|
|
5. Width of bed
|
10 feet
|
12 feet
|
|
6. Distance from disposal pipe to sidewall
|
3 feet
|
3 feet
|
|
7. Depth of cover over disposal pipe
|
9 inches
|
14 inches
|
|
8. Thickness of aggregate material under disposal
pipe
|
12 inches
|
No Maximum
|
|
9. Thickness of aggregate material over disposal
pipe
|
2 inches
|
2 inches
|
|
10. Slope of disposal pipe
|
Level
|
Level
|
|
11. Disposal pipe diameter
|
3 inches
|
4 inches
|
|
Note:
1. The effective depth is the distance between the
bottom of the disposal pipe and the bottom of the bed.
|
4. Chamber technology. An applicant shall:
a. Calculate an effective chamber absorption
area to size the disposal works area and determine the number of chambers
needed. The effective absorption area of each chamber is calculated as follows:
A = (1.8 × B × L) + (2 × V ×
L)
i. "A" is the effective absorption
area of each chamber,
ii. "B" is the
exterior width of the bottom of the chamber,
iii. "V" is the vertical height of the
louvered side-wall of the chamber, and
iv. "L" is the length of the
chamber;
b. Calculate the
disposal works size and number of chambers from the effective absorption area
of each chamber and the soil absorption rates specified in
R18-9-A312(D);
c. Ensure that the sidewall of the chamber
provides at least 35 percent open area for sidewall credit and that the design
and construction minimizes the movement of fines into the chamber area. The
applicant shall not use filter fabric or geotextile against the sidewall
openings.
5. Seepage
pits. If allowed by
R18-9-A311(B)(1),
the applicant shall:
a. Design a seepage pit
to comply with
R18-9-A312(E)(1)
for minimum vertical separation distance;
b. Ensure that multiple seepage pit
installations are served through a distribution box approved by the Department
or connected in series with a watertight connection laid on undisturbed or
compacted soil. The applicant shall ensure that the outlet from the pit has a
sanitary tee with the vertical leg extending at least 12 inches below the
inlet;
c. Ensure that each seepage
pit is circular and has an excavated diameter of 4 to 6 feet. If multiple
seepage pits are installed, ensure that the minimum spacing between seepage pit
sidewalls is 12 feet or three times the diameter of the seepage pit, whichever
is greater. The applicant may use the alternative design procedure specified in
R18-9-A312(G)
for a proposed seepage pit more than 6 feet in diameter;
d. For a gravel filled seepage pit, backfill
the entire pit with aggregate. The applicant shall ensure that each pit has a
breather conductor pipe that consists of a perforated pipe at least 4 inches in
diameter, placed vertically within the backfill of the pit. The pipe shall
extend from the bottom of the pit to within 12 inches below ground
level;
e. For a lined, hollow
seepage pit, lay a concrete liner or a liner of a different protective material
in the pit on a firm foundation and fill excavation voids behind the liner with
at least 9 inches of aggregate;
f.
For the cover of a lined seepage pit, use an approved one or two piece
reinforced concrete slab with a minimum compressive strength of 2500 pounds per
square inch. The applicant shall ensure that the cover:
i. Is at least 5 inches thick and designed to
support an earth load of at least 400 pounds per square foot;
ii. Has a 12-inch square or diameter minimum
access hole with a plug or cap that is coated on the underside with an
protective bituminous seal, constructed of concrete with 15 percent to 18
percent fly ash content, or made of other nonpermeable protective material;
and
iii. Has a 4 inch or larger
inspection pipe placed vertically not more than 6 inches below ground
level;
g. Ensure that the
top of the seepage pit cover is 4 to inches below the surface of the
ground;
h. Install a vented inlet
fitting in every seepage pit to prevent flows into the seepage pit from
damaging the sidewall. An applicant may use a 1/4 bend fitting placed through
an opening in the top of the slab cover if a one or two piece concrete slab
cover inlet is used;
i. Bore
seepage pits five feet deeper than the proposed pit depth to verify underlying
soil characteristics and backfill the five feet of overdrill with low
permeability drill cuttings or other suitable material;
j. Backfill seepage pits that terminate in
gravelly, coarse sand zones five feet above the beginning of the zone with low
permeability drill cuttings or other suitable material;
k. Determine the minimum sidewall area for a
seepage pit from the design flow and the soil absorption rate derived from the
testing procedure described in
R18-9-A310(G) .
The effective absorption surface for a seepage pit is the sidewall area only.
The sidewall area is calculated using the following formula: A = 3.14 × D
× H
i. "A" is the minimum sidewall
area in square feet needed for the design flow and soil absorption rate for the
installation,
ii. "D" is the
diameter of the proposed seepage pit in feet,
iii. "H" is the vertical height in feet in
the seepage pit through which wastewater infiltrates native soil. The applicant
shall ensure that H is at least 10 feet for any seepage
pit.