A. The Department shall redetermine
eligibility for TC benefits and, if applicable, recalculate a TC benefit amount
when the assistance unit reports a change directly to the Department, when
someone acting on behalf of the assistance unit reports a change, or if an
automated system report reveals a change.
B. When a change results in either a decrease
in the cash benefit or renders the assistance unit ineligible for TC payments,
the Department shall effect the change within 10 days from the date the change
was reported, when possible, using one of the following methods:
1. Reduce the benefit or terminate
eligibility for the first possible month allowing time for notice of adverse
action requirements prescribed in
R6-13-141, without further verification, if there is sufficient and reliable information
to effect the change; or
2. Attempt
to obtain verification by the 10th day from the date the change was reported
when there is not sufficient information to effect the change without
additional verification. The Department shall:
a. Send the assistance unit a written request
for verification with a due date that is the 10th day from the date the
verification is requested; and
b.
Contact third parties to obtain the needed verification, when
possible.
C.
If the assistance unit fails to provide the requested verification by the due
date and does not request assistance from the Department to obtain the
verification, the Department shall terminate TC payments for the first possible
month, allowing time for notice of adverse action requirements prescribed in
R6-13-141.
D. When a reported change results in an
increase in the cash benefit, the Department shall effect the increase only
after the change has been verified. The Department shall send the assistance
unit a written request for verification with a due date that is 10 days from
the date the Department mails the written request, or otherwise transmits the
written request as provided by law.
1. When
the assistance unit provides the requested verification on or before the due
date, the Department shall increase the cash benefit for the first monthly
payment issued after the date the change is reported.
2. When the assistance unit provides the
requested verification after the due date, the Department shall increase the
cash benefit for the first monthly payment issued after the date the
verification is received.
3. When
the assistance unit does not provide the requested verification, the Department
shall not increase the cash benefit but shall continue issuing the current cash
benefit amount.