Cal. Code Regs. Tit. 22, § 66265.1060 - Standards: Closed-Vent Systems and Control Devices
(a) Owners and operators of closed-vent
systems and control devices subject to this article shall comply with the
provisions of section
66265.1033.
(b)
(1) The
owner or operator of an existing facility who cannot install a closed-vent
system and control device to comply with the provisions of this article on the
effective date that the facility becomes subject to the provisions of this
article must prepare an implementation schedule that includes dates by which
the closed-vent system and control device will be installed and in operation.
The controls must be installed as soon as possible, but the implementation
schedule may allow up to 30 months after the effective date that the facility
becomes subject to this article for installation and startup.
(2) Any units that begin operation after
December 21, 1990, and are subject to the provisions of this article when
operation begins, must comply with the rules immediately (i.e., must have
control devices installed and operating on startup of the affected unit); the
30-month implementation schedule does not apply.
(3) The owner or operator of any facility in
existence on the effective date of a statutory or Department regulatory
amendment that renders the facility subject to this article shall comply with
all requirements of this article as soon as practicable but no later than 30
months after the amendment's effective date. When control equipment required by
this article cannot be installed and begin operation by the effective date of
the amendment, the facility owner or operator shall prepare an implementation
schedule that includes the following information: Specific calendar dates for
award of contracts or issuance of purchase orders for the control equipment,
initiation of on-site installation of the control equipment, completion of the
control equipment installation, and performance of any testing to demonstrate
that the installed equipment meets the applicable standards of this article.
The owner or operator shall enter the implementation schedule in the operating
record or in a permanent, readily available file located at the
facility.
(4) Owners and operators
of facilities and units that become newly subject to the requirements of this
article after December 8, 1997 due to an action other than those described in
subsection (b)(3) of this section must comply with all applicable requirements
immediately (i.e., must have control devices installed and operating on the
date the facility or unit becomes subject to this article; the 30-month
implementation schedule does not apply).
Notes
2. Change without regulatory effect repealing section, adding new section and amending NOTE filed 6-11-99 pursuant to Health and Safety Code section 25159.1 (Register 99, No. 24).
Note: Authority cited: Sections 25150, 25159, 25159.5, 25245 and 58012, Health and Safety Code. Reference: Sections 25150, 25159 and 25159.5, Health and Safety Code; and 40 CFR, Section 265.1060.
2. Change without regulatory effect repealing section, adding new section and amending Note filed 6-11-99 pursuant to Health and Safety Code section 25159.1 (Register 99, No. 24).
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.