Fla. Admin. Code Ann. R. 40A-44.052 - Authorization for Certain Forestry Projects
(1) Authorization is hereby granted, subject
to the general and specific conditions of this section, to any person who is
engaged in forestry operations to conduct the minor works described below:
(a) Culvert placement, replacement and
maintenance, in streams of less than 10 cubic feet per second average discharge
at the culvert location or streams draining less than 10 square miles, except
for culverts associated with low water crossings, provided that construction
does not cause scour in the downstream waters or increase the velocity of the
water downstream.
(b) Bridge
construction, replacement and maintenance for structures up to 400 feet in
length and two lanes or less in width supported by pilings or trestles where
the effects of pollutants discharged into open waters can be
minimized.
(c) Construction and
maintenance of low water crossings (hard surface crossings over which water
flows during storm events or immediately thereafter) provided construction does
not cause scour in the downstream waters or increase the velocity of the water
downstream.
(d) Temporary stream
channel diversions necessary to complete projects detailed in paragraphs (a),
(b) and (c), above, provided the area used for the temporary diversion is
restored to its previous contours and elevations.
(e) Channel clearing and shaping to
facilitate maximum hydraulic efficiency of designed structure detailed in
paragraphs (a), (b) and (c), above.
(f) Site preparation and access roads on
existing forestry lands including any ditch constructed or maintained with a
total cross-sectional area at the outfall of less than 35 square feet when a
berm or buffer zone of vegetation separates the site being prepared and the
open water. Where an access road crosses open water, the crossing construction
shall be in accordance with paragraph (a), (b), (c), (d) or (e),
above.
(2) Prior to the
construction, replacement, or maintenance of a minor forestry work authorized
under this section, notice shall be given to the District as follows:
(a) A completed Forestry Authorization
Notification Form, No. A44-F, effective 7-1-92, which is hereby incorporated by
reference, and copies of which can be obtained from
http://www.flrules.org/Gateway/Reference.asp?No=Ref-02969,
the District office identified below, or by electronic submittal at the
District's website www.nwfwater.com,
shall be submitted to the District no less than two (2) working days prior to
the commencement of work. For notification forms mailed to the District, the
postmark date shall be the date of submittal.
(b) Emergency notification will be allowed
under this section provided the District receives a completed Forestry
Authorization Notification Form or is notified by telephone prior to the
commencement of work. Telephone notification shall be followed by submittal of
a completed Forestry Authorization Notification Form no less than two (2)
working days after such telephone notification. A serious set of unforeseen or
unforeseeable circumstances must exist to create an emergency. Mere
carelessness or lack of planning on the part of the applicant shall not be
sufficient grounds to warrant the granting of emergency
authorizations.
(c) All forestry
authorization notifications shall be made to the District office identified
below:
Northwest Florida Water Management District
DeFuniak Springs Field Office
700 US Highway 331 S
DeFuniak Springs, FL 32435
(d) The person seeking an authorization, in
lieu of an individual project notification, may submit a yearly work plan
authorization request. The required plan shall be filed with the DeFuniak
Springs Service Office and shall identify the type, location and implementation
timetable for each proposed minor work authorized under the provisions of this
section. Yearly work plans shall be submitted thirty (30) days prior to the
commencement of the implementation of the identified works and may be modified
under individual project authorizations.
(3) This authorization shall be subject to
the general conditions of subsection
40A-44.301(2),
F.A.C, and the following specific conditions:
(a) Notice has been filed with the District
as provided for in subsection
40A-44.052(2),
F.A.C.
(b) The person shall use
Best Management Practices for Forestry as defined in subsection
40A-44.021(2),
F.A.C.
(c) The person shall
stabilize fill areas and stream banks disturbed by the activity by revegetation
or riprap as appropriate.
(d) The
person shall limit stream channel relocation to streams which have an average
annual discharge of 10 cubic feet per second or less. The length of relocated
channels or those significantly altered shall be limited to 200 feet per
stream. A stream channel shall be altered only when such a measure will reduce
the long term adverse water quality impacts and will maintain or restore the
stream's natural hydraulic capability.
(e) The person shall limit bridge
construction to those bridges spanning bank to bank with no causeway approaches
in the floodplain unless there are sufficient culverts in the causeway to
prevent downstream scour or increase in the velocity of the water downstream.
This limitation does not apply to maintenance of existing bridges or to the
construction of temporary log and pole bridges.
(f) The person shall limit crossings of any
particular stream to an average of one every 1/2 mile.
(4) This authorization does not apply to
activities which convert waters in the state to uplands by draining the land,
site preparation or other practices designed to bring an area not used for
forestry into such use or forest land into other uses. However, it shall apply
to activities on areas lying fallow as part of a conventional rotation cycle of
an established forestry operation. An operation ceases to be established when
the area on which it was conducted has been converted to another use or has
lain idle more than 5 years.
(5) If
at any time the District discovers that an Authorization has been used to
conduct minor forestry works which do not qualify for an Authorization under
this section, or an authorized activity is not being conducted in accordance
with the conditions described in this section, the District shall either
require application for a permit pursuant to Chapter 62-330, 40A-6 or 40A-44,
F.A.C., or shall take administrative or judicial enforcement action, or any
combination thereof, as it deems appropriate.
Notes
Rulemaking Authority 373.044, 373.113, 373.418 FS. Law Implemented 373.118, 373.406(5), 373.413, 373.416, 373.426 FS.
New 10-1-84, Amended 9-15-86, 8-1-89, 7-1-92, 8-6-13, 3-27-17.