Fla. Admin. Code Ann. R. 59A-4.134 - Plans Submission and Fee Requirements
(1) No construction work, including
demolition, shall be started until prior written approval has been provided by
the Agency's Office of Plans and Construction. This includes all construction
of new facilities and all additions, modifications, alterations, renovations,
and refurbishing to the site, facility, equipment or systems of all existing
facilities.
(2) Approval to start
construction only for demolition, site work, foundation, and building
structural frame may be obtained prior to construction document approval when
the following is submitted for review and approval:
(a) Preliminary Stage II approval letter from
the Agency's Office of Plans and Construction.
(b) Construction documents and specifications
for all work to be undertaken.
(c)
A life safety plan indicating temporary egress and detailed phasing plans
indicating how the areas to be demolished or constructed are to be separated
from all occupied areas when demolition or construction is in and around
occupied buildings.
(3)
Projects that have been submitted to the Agency for review will be considered
abandoned and will be terminated after any of the following has occurred:
(a) Construction has not begun within one
year after written approval of the construction documents from the Agency's
Office of Plans and Construction;
(b) No further plans have been submitted for
Agency review within one year after a project has been initiated with the
Agency's Office of Plans and Construction;
(c) Construction has been halted for more
than one year. After termination, resubmission as a new project will be
required.
(4) When
construction is planned, either for new buildings, additions, alterations or
renovations to existing buildings, the plans and specifications must be
prepared and submitted to the Agency's Office of Plans and Construction for
approval by a Florida registered architect and a Florida registered
professional engineer. An architecture or engineering firm, not practicing as a
sole proprietor, must provide proof of registration as an architecture or
engineering firm with the Florida Department of Business and Professional
Regulation.
(5) The initial
submission of plans to the Agency's Office of Plans and Construction for any
new project must include a completed Application for Plan Review, AHCA Form
3500-0011, June 2014, incorporated by reference and available at
http://www.flrules.org/Gateway/reference.asp?No=Ref-06024,
and from the Agency for Health Care Administration, 2727 Mahan Drive, MS #24,
Tallahassee, Florida 32308 or at the web address at
http://ahca.myflorida.com/plansandconstruction, and a valid Certificate of Need
or exemption as required by Sections
408.031 through
408.045, F.S. This information
must accompany the initial submission. Approval will not be granted for any
project without a Certificate of Need as required by Rule
59C-1.004, F.A.C.
(6) Plans and specifications submitted for
review shall be subjected to plan review fees pursuant to Section
400.232, F.S. A non-refundable
initial fee of $2, 000 will be charged for all projects. The agency will also
collect a fee, not to exceed 1 percent of the estimated construction cost or
the actual cost of review, whichever is less, for the portion of the review
which encompasses initial review through the initial revised construction
document review. Additionally, the Agency will collect its actual costs on all
subsequent portions of the review and construction inspections. All fees must
be paid to the Agency for Health Care Administration, with notation of the
Office of Plans and Construction facility log number and identified that it is
for the Agency's Health Care Trust Fund. Plan review fees must be included with
the application.
(7) Plans and
specifications may be submitted in three stages of development described in
this rule. Approval of a Stage III submission is required to begin construction
(except as permitted by subsection
59A-4.134(2),
F.A.C.). These stages are as follows:
(a)
Stage I, schematic plans.
(b) Stage
II, preliminary plans or design development drawings.
(c) Stage III, construction documents,
including specifications, addenda and change orders.
(8) For each stage of submission, a program
or scope of work must be submitted.
(9) For projects involving only equipment
changes or system renovations, construction documents need to be submitted.
These documents must include the following:
(a) Life safety plans showing the fire/smoke
compartments in the area of renovation.
(b) Detailed phasing plans indicating how the
new work will be separated from all occupied areas.
(c) Engineering plans and specifications for
all of the required work.
(10) Stage I, Schematic Plans - The following
must be incorporated into the schematic plans:
(a) Single-line drawings of each floor that
must show the relationship of the various activities or services to each other
and each room arrangement. The function of each room or space must be noted in
or near the room or space. The proposed roads and walkways, service and
entrance courts, parking, and orientation must be shown on either a small plot
plan or on the first floor plan. Provide a simple cross-section diagram showing
the anticipated construction. Provide a schematic life safety plan showing
smoke and fire compartments, exits, exit passageways and gross area of smoke
and fire compartments. Provide information as to which areas have sprinklers,
both new and existing.
(b) If the
proposed construction is an addition or is otherwise related to existing
buildings on the site, the schematic plans must show the facility and general
arrangement of those other buildings.
(c) A schedule showing the total number of
beds, types of bedrooms and types of ancillary spaces.
(11) Stage II, Preliminary Plans - Stage II
preliminary plans will be approved by the Agency upon successful demonstration
that the construction will comply with applicable life safety code
requirements, flood requirements and that the layout will accommodate all
required functional space as evidenced by a thorough examination of the
documents submitted as required by this subsection. Stage IIpreliminary plans
must include:
(a) A vicinity map showing the
major local highway intersections for new nursing home construction.
(b) Site development plans that:
1. Show existing grades and proposed
improvement as required by the schematic submission.
2. Provide building locating
dimensions.
3. Provide site
elevations for both the 100 year flood elevations and hurricane category 3
surge inundation elevations if the project involves the construction of a new
facility or is a new addition of a wing or floor to an existing
facility.
4. Provide the location
of the fire protection services water source to the
building.
(c)
Architectural plan that include:
1. Floor
plans, 1/8-inch scale minimum, showing door swings, windows, casework and
millwork, fixed equipment and plumbing fixtures. Indicate the function of each
space.
2. A large-scale plan of
typical new bedrooms with tabulation of gross and net square footage of each
bedroom. Tabulate the size of the bedroom window glass.
3. Typical large-scale interior and exterior
wall sections to include typical rated fire and fire/smoke partitions and a
typical corridor partition.
4. All
exterior building elevations.
5.
Equipment that is not included in the construction contract but that requires
mechanical or electrical service connections or construction modifications must
be identified to assure its coordination with the architectural, mechanical and
electrical phases of construction.
6. If the project is located in an occupied
facility, preliminary phasing plans indicating how the project is to be
separated from all occupied areas.
(d) Life safety plans that include:
1. Single-sheet floor plans showing fire and
smoke compartmentation, all means of egress and all exit signs. Additionally,
depict and provide the dimension for the longest path of travel in each smoke
compartment to the door(s) to the adjoining compartment, calculate the total
area of the smoke compartment in square feet, and tabulate exit
inches.
2. All sprinklered areas,
fire extinguishers, fire alarm devices and pull station locations.
3. Fully developed life safety plans, if the
project is an addition or conversion of an existing building.
4. Life safety plans of the floor being
renovated and required exit egress floor(s) if the project is a renovation in
an existing building.
5. When
demolition or construction is to be undertaken in and around occupied
buildings, a life safety plan indicating temporary egress and detailed phasing
plans indicating how the areas to be demolished or constructed are to be
separated from all occupied areas.
(e) Mechanical engineering plans that
include:
1. Single-sheet floor plans with a
one-line diagram of the ventilating system with relative pressures of each
space. Provide a written description and drawings of the anticipated smoke
control system, passive or active, and a sequence of operation correlated with
the life safety plans.
2. The
general location of all fire and smoke dampers, all duct smoke detectors and
fire stats.
3. If the building is
equipped with fire sprinklers, the location of the sprinkler system risers and
the point of connection for the fire sprinkler system. State the method of
design for the existing and new fire sprinkler systems.
4. The locations of all plumbing fixtures and
other items of equipment requiring plumbing services and/or gas
service.
5. The locations of any
fume, radiological or chemical hoods.
6. The locations of all medical gas outlets,
piping distribution risers, terminals, alarm panels, low pressure emergency
oxygen connection, isolation/zone valves, and gas source locations.
7. The locations and relative size of major
items of mechanical equipment such as chillers, air handling units, fire pumps,
medical gas storage, boilers, vacuum pumps, air compressors and fuel storage
vessels.
8. The locations of
hazardous areas and the volume of products to be contained therein.
9. The location of fire pump, stand pipes,
and sprinkler risers.
(f)
Electrical engineering drawings that include:
1. A one-line diagram of normal and essential
electrical power systems showing service transformers and entrances,
switchboards, transfer switches, distribution feeders and over-current devices,
panel boards and step-down transformers. The diagram must include a preliminary
listing and description of new and existing, normal and emergency loads,
preliminary estimates of available short-circuit current at all new equipment
and existing equipment serving any new equipment, short-circuit and withstand
ratings of existing equipment serving new loads and any new or revised
grounding requirements.
2. Fire
alarm zones and correlate with the life safety plan.
(g) Outline specifications are to include a
general description of the construction, including construction classification
and ratings of components, interior finishes, general types and locations of
acoustical material, floor coverings, electrical equipment, ventilating
equipment and plumbing fixtures, fire protection equipment, and medical gas
equipment.
(h) Whenever an existing
building is to be converted to a health care facility, the general layout of
spaces of the existing structure must be submitted with the preliminary plans
for the proposed facility.
(i)
Whenever additions, modifications, alterations, renovations, and refurbishing
to an existing building are proposed, the general layout of spaces of the
existing facility must be submitted with the preliminary
plans.
(12) Stage III,
Construction Documents - The Stage III construction documents shall be an
extension of the Stage II preliminary plan submission and shall provide a
complete description of the contemplated construction. Stage III construction
documents will be approved by the Agency upon successful demonstration that the
construction will comply with all applicable codes and standards as evidenced
by a thorough examination of the documents submitted as required by this
subsection. Construction documents shall be signed, sealed, dated and submitted
for written approval to the Agency's Office of Plans and Construction submitted
by a Florida registered architect and Florida registered professional engineer.
An architecture or engineering firm, not practicing as a sole proprietor, must
provide proof of registration as an architecture or engineering firm with the
Florida Department of Business and Professional Regulation. The documents must
consist of work related to civil, structural, mechanical, and electrical
engineering, fire protection, lightning protection, landscape architecture and
all architectural work. In addition to the requirements for Stage II
submission, the following must be incorporated into the construction documents:
(a) Site and civil engineering plans that
indicate building and site elevations, site utilities, paving plans, grading
and drainage plans and details, locations of the two fire hydrants utilized to
perform the water supply flow test, and landscaping plans.
(b) Life safety plans for the entire
project.
(c) Architectural plans.
1. Typical large-scale details of all typical
interior and exterior walls and smoke walls, horizontal exist and exit
passageways.
2. Comprehensive
ceiling plans that show all utilities, lighting fixtures, smoke detectors,
ventilation devices, sprinkler head locations and fire-rated ceiling suspension
member locations where applicable.
3. Floor/ceiling and roof/ceiling assembly
descriptions for all conditions.
4.
Details and other instructions to the contract on the construction documents
describing the techniques to be used to seal floor construction penetrations to
the extent necessary to prevent smoke migration from floor to floor during a
fire.
(d) Structural
engineering plans, schedules and details.
(e) Mechanical engineering plans to include
fire and smoke control plans. Show all items of owner furnished equipment
requiring mechanical services. Provide a clear and concise narrative control
sequence of operations for each item of mechanical equipment including: air
conditioning, heating, ventilation, medical gas, plumbing, and fire protection
and any interconnection of the equipment of the systems. Mechanical engineering
drawings must depict completely the systems to be utilized, whether new or
existing, from the point of system origination to its termination. Provide a
tubular schedule giving the required air flow (as computed from the information
contained on the ventilation rate table) in cubic feet per minute (cfm) for
supply, return, exhaust, outdoor, and ventilation air for each space listed or
referenced by note on the ventilation rate table as shown on the architectural
documents. The schedule must also contain the Heating Ventilation and Air
Conditioning (HVAC) system design air flow rates and the resulting space
relative pressures. The schedule or portion of the schedule, as applicable,
must be placed in the specifications or in the drawing set containing the
spaces depicted.
(f) Fire
protection plans, where applicable, that must include the existing system as
necessary to define the new work.
(g) Electrical engineering plans that must
describe complete power, lighting, alarm, communications and lightning
protection systems and power system study.
(h) A power study that must include a fault
study complete with calculations to demonstrate that over-current devices,
transfer switches, switchboards, panel boards, motor controls, transformers and
feeders are adequately sized to safely withstand available phase-to-phase and
phase-to-ground faults. The study must also include an analysis of generator
performance under fault conditions and a coordination study resulting in the
tabulation of settings for all over-current device adjustable trips, time
delays, relays and ground fault coordination. This must be provided for all new
equipment and existing equipment serving any new equipment. Power studies for
renovations of existing distribution systems must include only new equipment
and existing equipment upstream to the normal and emergency sources of the new
equipment. Renovations involving only branch circuit panel boards without
modifications to the feeder will not require a full power study; instead, the
power study will be limited to the calculation of new and existing loads of the
branch circuit panel.
(i) A
complete set of specifications of all work to be undertaken.
1. All project required contractor supplied
testing and/or certification reports must be submitted in type written format,
on standard forms, reviewed and accepted by the Engineer of Record prior to
presenting to the Agency for review.
2. The specifications must require a
performance verification test and balance air quality value report for two
operating conditions for each air handling unit system. One operating condition
must be with the specified air filters installed in the minimum pressure drop
or clean state. The second operating condition must be at the maximum pressure
drop and/or dirty state. The air quantities reported are acceptable if they are
within ten percent of the design value and the space relative pressures are
maintained. This requirement applies to any air-handling unit affected by the
construction to be performed.
(j) Well-coordinated construction documents.
In the case of additions to existing institutions, the mechanical and
electrical, especially existing essential electrical systems and all other
pertinent conditions must be a part of this submission.
(k) Signed, sealed and dated subsequent
addenda, change orders, field orders and other documents altering the above
must be submitted for review to the Agency's Office of Plans and Construction.
The Agency will either approve or disapprove the submission based on compliance
with all applicable codes and standards and will provide a listing of
deficiencies in writing.
(13) Initial submissions will be acted upon
by the Agency within 60 days of the receipt of the initial payment of the plan
review fee. The Agency will either approve or disapprove the submission and
will provide a listing of deficiencies in writing. Each subsequent resubmission
of documents for review on the project will initiate another 60-day response
period. All deficiencies noted by the Agency must be satisfactorily corrected
before final construction approval can be obtained for the project from the
Agency.
(14) Additions that increase
the scope of the project by greater than fifty percent or revisions that change
greater than fifity percent of the original scope of a project will be required
to be submitted as a new project.
(15) Within 60 days after final approval of
the project has been obtained from the Agency, the licensee and the Agency's
Office of Plans and Construction must be provided with a complete set of record
drawings electronically submitted as Portable Document Format (.pdf) files
showing all of the construction, fixed equipment and the mechanical and
electrical systems as installed. These electronically submitted .pdf files must
include the life safety plans of the facility.
Notes
Rulemaking Authority 400.23 FS. Law Implemented 400.141, 400.232 FS.
New 12-21-15.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.