Fla. Admin. Code Ann. R. 59C-1.018 - Termination of Certificate of Need
(1)
Validity Period of Certificate of Need. A Certificate of Need shall terminate
18 months from the date of issuance unless the holder meets the applicable
conditions for an extension set forth in Section
408.040(2),
F.S., and this rule.
(2) Undertaking
a Project Authorized by a Certificate of Need. A Certificate of Need will
terminate after the 18-month time frame set forth in subsection (1) unless the
applicant meets one of the minimum requirements described below:
(a) Certificates of Need for New Construction
or Renovation Projects.
1. A holder of a
Certificate of Need with a project for new construction must, by the date of
termination of the Certificate of Need, be deemed to have commenced continuous
construction as defined in Section
408.032(4),
F.S. For purposes of compliance, site preparation must be completed as defined
below:
a. Completion of site preparation
activities which include clearing of land, removal of soil, placement and
compacting of fill dirt, and grading and leveling of the site for that portion
of the site which will contain the foundation;
b. Foundation permit;
c. Completion of footprint of the
certificated portion of the building, unless the contractor is building a
hospital using the fast-track method of construction and the agreement between
the contractor and the Certificate of Need holder provides for the use of that
method; and,
d. Foundation forming
with placement of concrete and steel which will become an integral part of the
final facility to be constructed.
2. A holder of a Certificate of Need for
renovation of an existing structure must, by the date of termination of the
Certificate of Need, be deemed to have commenced construction. This is
established by completing site preparation which is defined as having a
demolition permit or building permit, having an executed owner or contractor
agreement, and demonstrating proof of the commencement of demolition.
3. The Agency staff or a designated
representative shall make an unannounced visit to each project site on the
termination date of the Certificate of Need. The visit shall result in
photographs of the site and a written report. The Certificate of Need holder
may submit information for evaluation to the staff of the Agency or the
designated representative on the day of the site visit. On or before 14
calendar days of receipt of the information, staff designated by the Agency
shall evaluate the information and make a determination of whether or not the
project has commenced construction.
a. If
deemed to have commenced construction, continuous construction must be
maintained. For purposes of monitoring compliance, "continuous construction"
refers to work performed under the authority of an architect to whom the
contractor is responsible and which advances the project towards completion in
accordance with the project timetable and standard, acceptable construction
procedures. Any return to site preparation as defined in sub-subparagraphs
59C-1.018(2)(a)
1.a.-d., F.A.C., without approval, as provided in paragraphs
59C-1.021(2)(a) and
(b), F.A.C., of the Agency is strictly
prohibited and is deemed not to be continuous construction.
b. If deemed not to have commenced
construction, the holder of the Certificate of Need shall be notified, in
writing, of the determination and the right to a hearing under Section
120.57, F.S., by the director or
his or her designee from the Agency. The Certificate of Need shall terminate by
operation of law.
(b) Certificates of Need for Non-construction
Projects.
1. A holder of a Certificate of Need
for a non-construction project including Hospice, bed conversions and
establishment of new health services, or a substantial change in such services,
must provide proof of having made an enforceable capital expenditure greater
than 10% percent of the total project cost, or have received appropriate
licensure and certification by the date of termination of the Certificate of
Need.
2. A holder of a Certificate
of Need who undertook a project authorizing the offering of a new service for
which there is neither construction nor enforceable capital expenditure must
provide utilization data to the Agency within 30 calendar days after the
termination date of the Certificate of Need. The data must demonstrate that the
service became operational on or before the termination date of the Certificate
of Need.
(3)
Extension of Validity Period.
(a) Extensions
of up to 60 calendar days per each request may be requested by a Certificate of
Need holder who is approaching the end of the 18-month validity period. The
holder must submit a written request to the Agency for approval at least 15
calendar days before the Certificate of Need terminates. The filing of a
request does not extend the validity period of a Certificate of Need. Failure
to timely file is a waiver of the right to request an extension. This request
for an extension must demonstrate that good faith commencement of the project
is being delayed by litigation or by governmental action or inaction with
respect to regulations or permitting which precludes commencement on the
project. The request must provide the Agency a detailed explanation of the
problem and a plan of action to be undertaken by the holder to resolve the
problem within the time frame requested.
1.
Land zoning issues will be considered for extension of the Certificate of Need
validity period beyond the 18 months, if the Certificate of Need holder can
demonstrate that action has been initiated to obtain proper zoning for the
proposed site for the facility, and that such action was timely with respect to
the requirements for obtaining proper zoning.
2. Untimely filing of submission of plans and
requests for local and state permits, based on the processing time required by
the state and local governments for such plans and permits, will not be
considered as justification for an extension beyond the 18-month
period.
(b) Where the
holder of a valid Certificate of Need is precluded from commencement of the
project due to litigation, including appeal, or if the holder's Certificate of
Need is the subject of an appeal of a final order approving the issuance of the
Certificate of Need, an extension of the validity period shall be granted for
the actual amount of time of the validity period which is equivalent to the
period of litigation, including appeal. The holder of a Certificate of Need
shall submit a request for an extension to the Agency, in writing, not later
than 15 calendar days prior to the termination date.
(c) Upon written request from the holder of a
Certificate of Need received at least 15 days prior to the termination date of
the Certificate of Need, and upon submission of a transfer application by the
proposed transferee, the Agency will extend the validity period of the proposed
transferred Certificate of Need for a period of 60 days to ensure that the
Certificate of Need remains valid throughout the Agency's timetable for review
of the transfer application. Only one such request for a 60 day extension will
be granted under the provisions of this
subsection.
Notes
Rulemaking Authority 408.034(8), 408.15(8) FS. Law Implemented 408.040(2) FS.
New 11-24-86, Amended 7-25-89, Formerly 10-5.018, Amended 10-8-97, 12-12-00.