The words and phrases in this chapter shall be construed
according to their plain meaning, in light of the context and subject matter,
unless expressly defined otherwise in this rule, this chapter, or in Chapter
255, F.S.
(1) "Agency", as the context
requires, means an official, officer, commission, authority, council,
committee, department, division, bureau, board, section or other unit or entity
of state government.
(2) "Contract
Levels" - increments of contract dollar value based on estimated cost of the
contract are as follows:
(a) Level One -
Contracts not exceeding a value of $35, 000.
(b) Level Two - Contracts having a value
greater than $35, 000 but not exceeding $65, 000.
(c) Level Three - Contracts having a value
greater than $65, 000 but not exceeding $200, 000.
(d) Level Four - Contracts having a value
exceeding $200, 000 but not exceeding $500, 000.
(e) Level Five - Contracts having a value
exceeding $500, 000.
(3)
The "Agency Head" - The person or in the case of a collegial body the executive
director or chief administrative officer of an Agency or other governmental
unit statutorily responsible for final agency action, or their authorized
designee.
(4) The "Division" means
a program of the Department as identified in Section
20.22(2)(a),
F.S.
(5) "Firm" or "Contractor"
means any individual, firm, partnership, corporation, company, association, or
other legal entity permitted by law to construct projects, or portions of
projects, in the State of Florida.
(6) "Project" means any facility, building,
portion of building, utility, park, parking lot, structure or other improvement
to real property required to be constructed, renovated, repaired, modified or
demolished by an Agency.
(7)
"Design Professional" means the architect, engineer or other consultant under
contract with the Agency for professional services.
(8) "Non-material Bid Deviation" means a
variation from the invitation to bid terms and conditions which does not affect
the price of the bid, or give the bidder an advantage or benefit not enjoyed by
other bidders, or does not adversely impact the interests of the
Agency.
(9) "Single Source
Contract" means a contract for construction services that are available from
only one responsible qualified contractor.
(10) "Valid Bid" means a bid that is
responsive to the bidding documents and is submitted by a qualified responsible
bidder. The validity of the bid is determined by the Agency and the
construction management entity.
(11) "Negotiated Fee-Guaranteed Maximum Price
Construction Contracting Method" means a method of construction contracting
whereby the construction management entity is selected by the methods defined
under Rule
60D-5.0082, F.A.C., to provide
design phase consulting services, management and contractual responsibility for
the total project. A fee is negotiated for profit, overhead and direct
management costs. All subcontracts are awarded by the construction management
entity based on competitive bids received in response to invitations to bid
issued by the construction management entity. A guaranteed maximum price is
provided by the construction management entity and the total price paid to the
construction management entity is either the fee plus the actual construction
cost or the guaranteed maximum price (GMP), whichever is less.
(12) "Guaranteed Maximum Price" means the
fixed amount in a negotiated fee-guaranteed maximum price contract within which
the construction will be achieved. It includes all fees, profit, overhead
direct management costs, and the construction cost.
(13) "Repairs" means the restoration to an
acceptable original state of a decayed, broken, deteriorated or demolished
facility, building, portion of building, utility, park, parking lot, structure
or other real property.
(14)
"Maintenance" means the upkeep, preservation of condition or the sustaining of
operation of a facility, building, portion of building, utility, park, parking
lot, structure or real property.
(15) "Client Agency" means that Agency for
which the project is being constructed.
(16) "Responsive Bidder" means a firm who has
submitted a bid or proposal which conforms in all material respects to the
invitation to bid or request for proposals.
(17) "Responsible bidder" or "qualified
bidder" means a firm with the capability in all respects to perform fully the
contract requirements and the integrity and reliability to assure good faith
performance.