Fla. Admin. Code Ann. R. 60GG-1.002 - Risk and Complexity Assessment
(1)
The Agency will perform Risk & Complexity Assessments (R&C Assessments)
for information technology (IT) projects to evaluate the risk and complexity
factors for each IT project
https://www.flrules.org/Gateway/reference.asp?No=Ref-05569.
The purpose of the assessments is to determine the minimum level of project
management control necessary to manage a given project in order to reduce risk
and increase the probability of success.
(2) These assessments align projects by risk
and complexity levels into one (1) of four (4) Risk and Complexity (R&C)
Categories, which determine the amount of project management control required.
The following diagram indicates the distribution of risk and complexity levels
into the R&C Category:
|
Complexity |
||||
|
Low |
Medium |
High |
||
|
Risk |
Low |
1 |
1 |
2 |
|
Medium |
2 |
2 |
3 |
|
|
High |
3 |
3 |
4 |
|
(a) Category 4
represents High Risk and High Complexity projects.
(b) Category 3 represents High Risk and
Medium Complexity projects, High Risk and Low Complexity projects, or Medium
Risk and High Complexity projects.
(c) Category 2 represents Medium Risk and
Medium Complexity projects, Medium Risk and Low Complexity projects, or Low
Risk and High Complexity projects.
(d) Category 1 represents Low Risk and Medium
Complexity projects or Low Risk and Low Complexity projects.
(e) Specific lifecycle phase requirements for
each category are identified in Rule 60GG-1.003, F.A.C. - Initiation; Rule
60GG-1.004, F.A.C. - Planning; Rule 60GG-1.005, F.A.C. - Execution; Rule
60GG-1.006, F.A.C. - Monitoring and Controlling; and Rule 60GG-1.007, F.A.C. -
Closure.
(3) The R&C
Assessments are conducted using Form DMS-F-0505A, DMS Risk & Complexity
Assessment Workbook (07/15). This workbook is used by Agencies to determine the
cumulative R&C Category designation. The R&C Assessment Workbook is
divided into seven (7) separate assessment worksheets which are conducted at
four (4) key points in the project management life cycle. Form DMS-F-0505A, DMS
Risk & Complexity Assessment Workbook, is hereby incorporated by reference
in this rule.
(a) The Agency must complete a
Pre-Charter R&C Assessment (consisting of a Risk worksheet and a Complexity
worksheet) at the start of the Initiation phase of the project. During this
assessment, the Agency will review priorities and business need, assess the
project, and analyze factors that might impact project success. The resulting
R&C Category establishes the project management control requirements to be
applied during the project Initiation phase. (See Rule 60GG-1.003, F.A.C. -
Initiation)
(b) The Agency must
complete an Initiation Gate R&C Assessment at the end of the Initiation
phase following completion of project Initation documentation. During this
assessment, the Agency will review Initiation documents, validate or amend the
previous R&C assessment findings, and complete the Initiation Gate R&C
Assessment (consisting of a Risk worksheet and a Complexity worksheet). This
assessment will confirm or adjust the project's cumulative risk &
complexity level and resulting R&C Category, examine the effectiveness of
Initiation phase activities, and set requirements for the project Planning
phase. (See Rule 60GG-1.004, F.A.C. - Planning)
(c) The Agency must complete a Planning Gate
R&C Assessment at the end of the Planning phase, following completion of
project planning documentation. During this assessment, the Agency will review
project documents, validate or amend the previous R&C assessment findings,
and complete the Planning Gate R&C Assessment (consisting of a Risk
worksheet and a Complexity worksheet). This assessment will confirm or adjust
the project's cumulative risk and complexity level and resulting R&C
Category, examine the effectiveness of Planning phase activities, and set
requirements for the project Execution and Monitoring and Controlling phases.
(See Rule 60GG-1.005, F.A.C. - Execution, and Rule 60GG-1.006, F.A.C.
-Monitoring and Controlling)
(d)
The Agency must complete an Event-Driven R&C Assessment if the project
experiences a significant change, or cumulative changes (in cost, schedule, or
scope) from the project baseline. During this assessment, the Agency will
review the change control request(s) and project documentation. The Agency will
also review, validate or amend the previous R&C assessment findings, and
complete the Event-Driven R&C Assessment (consisting of a Risk worksheet).
This assessment will confirm or adjust the project's cumulative risk &
complexity level and resulting R&C Category and determine if review and
amendment to project management baselines are
needed.