Fla. Admin. Code Ann. R. 62-330.451 - General Permit to Counties, Municipalities, and other Agencies to Conduct Stormwater Retrofit Activities
(1) A
general permit is granted to counties, municipalities, state agencies and water
management districts to construct, operate, and maintain stormwater retrofit
activities as authorized below for improving existing surface water and
stormwater systems. This general permit may be used in conjunction with exempt
activities.
(2) Types of stormwater
retrofit activities authorized under this general permit are:
(a) Construction or alteration that will add
additional treatment or attenuation capacity and capability to an existing
stormwater management system;
(b)
The modification, reconstruction, or relocation of an existing stormwater
management system or stormwater discharge facility;
(c) Stabilization of eroding banks, and
installation of structures such as gabions to limit bank erosion; or
(d) Excavation or dredging to remove
sediments or other pollutants that have accumulated in existing surface waters
as a result of stormwater runoff and stormwater discharges, provided the
material removed is not deposited in existing wetlands or other surface
waters.
(3) Stormwater
retrofit activities shall not:
(a) Be proposed
or implemented for the purpose of providing the water quality treatment or
flood control needed to serve new development or redevelopment; or
(b) Include a dam that has more than 50
acre-feet of storage capacity if the dam is more than five feet high, nor a dam
having a height of ten or more feet, regardless of storage capacity. Height is
measured from the top of the dam to the natural bed of the stream or
watercourse at the downward toe of the dam, or from the lowest elevation of the
outside limit of the dam to the maximum elevation of the
dam.
(4) There is no
limit to the acreage of stormwater retrofit activities in artificial waters.
Work in wetlands and non-artificial surface waters shall be limited to no more
than 0.5 acre.
(5) A stormwater
quality retrofit activity must result in at least one of the following:
(a) Addition of treatment capacity to an
existing stormwater management system such that it reduces stormwater pollutant
loadings to receiving waters;
(b)
Addition of treatment or attenuation capability to an existing developed area
when either the existing stormwater management system or the developed area has
substandard stormwater treatment or attenuation capabilities, compared to what
would be required for a new system requiring a permit under Part IV of Chapter
373, F.S.; or
(c) Removal of
pollutants generated by, or resulting from, previous stormwater
discharges.
(6) A water
quantity retrofit project proposed to reduce existing flooding problems must be
designed in such a way that the project does not:
(a) Result in a net reduction in water
quality treatment provided by the existing stormwater management system;
nor
(b) Increase discharges of
untreated stormwater entering receiving waters.
(7) The project must be designed,
constructed, and implemented as a complete, stand-alone project within the
construction phase duration of a general permit, and such that it will not at
any time during its construction or operation:
(a) Cause or contribute to any water quality
violations;
(b) Contribute to any
existing violation if it discharges pollutants into waters where existing
ambient water quality does not meet water quality standards for those
pollutants. In such a case, the project must include measures that will cause a
net improvement in the receiving waters for those pollutants in accordance with
Section 373.414(1)(b)3., F.S.;
(c)
Adversely affect the value of functions provided to fish and wildlife by
wetlands or other surface waters;
(d) Adversely affect the hydroperiod of
wetlands on adjacent lands or the hydroperiod of other wetlands upstream,
downstream, or adjoining to the work area under subsection (4),
above;
(e) Cause or contribute to
increased flooding of adjacent lands or cause new adverse water quantity
impacts to receiving waters;
(f)
Add or increase any chemical treatment;
(g) Be operated by pumps or other mechanical
or adjustable features; nor
(h)
Adversely impact the maintenance of surface or ground water levels or surface
water flows established pursuant to Section
373.042,
F.S.
(8) The entity
conducting this general permit must conduct at least one pre-notice meeting
with Agency staff having responsibility for the review of the proposed
activities. The notice required in Rule
62-330.402, F.A.C., shall
include materials reflecting the recommendations of the Agency discussed during
that meeting, and demonstrating compliance with the above, including a
certification by a registered professional that the proposed activity will meet
the criteria specified above. Such certification shall include appropriate
design analyses, pollutant loading analyses, modeling and other engineering
calculations, drawings, specifications and other information to support,
describe, verify, and document the registered professional's
certification.
(9) Nothing in this
general permit will preclude a county or municipality from obtaining and
implementing a Basin Management Action Plan with water quality credits for
activities performed under this authorization.
(10) Within 30 days after completion of
construction, a registered professional shall submit certification that
construction was completed in substantial conformance with the plans and
calculations that were submitted in the notice to use this general
permit.
Notes
Rulemaking Authority 373.026(7), 373.043, 373.118(1), 373.118(6), 373.406(5), 373.4131, 373.414(9), 373.418, 403.805(1) FS. Law Implemented 373.118(1), (6), 373.406(5), 373.413, 373.4131, 373.414(9), 373.416, 373.418 FS.
New 10-1-13, Amended 6-1-18.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.