(1)
Steps involved in obtaining a loan.
(a)
Request for inclusion. The project sponsor shall submit a Request for Inclusion
Form, incorporated by reference in subsection
62-503.200(33),
F.A.C., to the Department to establish project ranking on the priority list as
outlined in paragraph (1)(e), below, and to determine the financing rate on the
loan, as outlined in subsection (5), below:
1.
The Department shall review requests for inclusion to verify eligibility and
accuracy of the information provided, such as census tract numbers, service
area boundaries, population, public health risk, system boundaries, project
costs, and to determine the project scope.
2. Additional information shall be requested
by the Department when the data provided by the project sponsor are incomplete
or unclear.
(b)
Documentation required for priority listing. The documentation that must be
timely submitted to compete for funding at a priority list meeting varies
depending on the type of loan being requested and is known as the
readiness-to-proceed criteria. For planning loans, the completed Request for
Inclusion form and its necessary attachments are required. For design loans,
the Request for Inclusion form and all documentation required in subsection
62-503.700(2),
F.A.C., must be submitted and complete. For Inflow and Infiltration (I/I)
rehabilitation loans, the Request for Inclusion form, sewer system evaluation
study, all documentation referenced in Rule
62-503.751, F.A.C., all required
permits and bid documents corresponding to the areas to be rehabilitated must
be submitted. For construction loans, the Request for Inclusion form, all
documentation referenced in subsections
62-503.700(2)
through
62-503.700(5),
F.A.C., must be submitted, and the process described in Rule
62-503.751,
F.A.C., must be completed.
(c)
Priority List Public Meeting.
1. Except as
provided in subparagraph 2., below, if funds are available for new projects, a
priority list public meeting shall be held on the second Wednesday in August,
or as otherwise noticed in the Florida Administrative Register in advance of
the public meeting.
2. If the
waiting portion from the previous fiscal year exceeds twice the anticipated
available funds, no public meeting shall be held, unless it is necessary to add
projects to meet federal requirements. If such a public meeting is held, only
those projects necessary to comply with the federal requirements shall be
considered. For the purposes of this paragraph, anticipated available funds
means federal capitalization grants and state matching funds expected to be
received during the state fiscal year, loan repayments minus debt service
payments to be received during the state fiscal year, any carry over funds from
the previous year, and anticipated interest earnings during the fiscal
year.
3. If additional funds are
available after the priority list public meeting, one or more priority list
management public meetings shall be scheduled to allocate the additional
funds.
(d)
Readiness-to-proceed deadline. For a project to appear on the priority list,
the sponsor shall have postmarked or delivered to the Department all
documentation as required in paragraph (b) above and shall have the
Department's acceptance of its planning and environmental review process for a
design or construction loan no later than 45 days before the priority list
public meeting at which the project competes for funding. The project sponsor
must respond to all Department comments related to the required documentation
and must submit these responses at least 15 days prior to the public
meeting.
(e) Priority system.
Timely submitted projects shall be given priority according to the extent each
project is intended to remove, mitigate, or prevent adverse effects on surface
or ground water quality and public health. The final priority score for each
project shall be determined as described in subparagraphs 1. though 4., below.
1. Base priority score. Each project shall
receive a base priority score (BPS) based on the weighted average of its
components or facilities. The BPS shall be determined based on the following
formula where CPS means the component priority score and CCC means component
construction cost or:
|
BPS = [CPS1 x CCC1 + . . + CPSn x CCCn ] / Total
Construction Cost
|
|
Project components shall be assigned component
priority scores according to the categories in Table 1.
|
|
Table 1
|
|
Project Component
|
CPS
|
|
1. Eliminate a documented acute or chronic public
health hazard. Examples include eliminations of failing septic tanks, failing
package plants, or sanitary sewer overflows.
|
500 points
|
|
2. Implement a project included in, or to be
implemented as a direct result of, an adopted Basin Management Action Plan or a
Reasonable Assurance Plan approved pursuant to Section
403.067, F.S.
|
450 points
|
|
3a. Protect surface or ground water by preventing or
reducing a documented source of pollution, pollution reductions necessary to
meet regulatory requirements, or
3b. Projects or activities by local governmental
agencies or on-site system management entities, under section 319 of the Act,
that correct septic tank failures in springsheds of first-magnitude springs; or
correct septic tank contributions to nutrient impaired spring systems.
|
400 points
|
|
4. Address a compliance problem documented in an
enforcement action where the Department has issued a notice of violation or
entered into a consent order with the project sponsor.
|
375 points
|
|
5. Meet the criteria for a Green Project; correct
excessive inflow/infiltration or other issues within the collection and
transmission system that cause sanitary sewer overflows; scheduled
rehabilitation, replacement, or repair described in an approved asset
management plan; or reuse that replaces an existing or proposed demand on a
water supply.
|
350 points
|
|
6. Planning and design loans; projects for the
installation of wastewater transmission facilities to be constructed
concurrently with other construction projects occurring within or along a
transportation facility right-of-way; or for rehabilitation, replacement or
repair not included in an approved asset management plan.
|
340 points
|
|
7. Projects that construct other reclaimed water
systems or residuals reuse systems that do not meet the criteria of component
5., above.
|
300 points
|
|
8. Ensure compliance with other enforceable standards
or requirements.
|
200 points
|
|
9. Timely submitted project that otherwise meets the
requirements of the Act, including land or wastewater system
acquisition.
|
100 points
|
2.
Special waters of the state factor. A project base priority score assigned
under subparagraph (e)1., above, shall be multiplied by 1.2 if the project is a
construction project that will assist in the restoration or protection of
Outstanding Florida Waters (pursuant to Section
403.061, F.S.), a water body
identified under the National Estuary Program (pursuant to the Act); a
federally designated Wild, Scenic or Recreational River Area; or an impaired
water body on the State's adopted verified list of impaired waters.
3. Construction projects that result in the
elimination of ocean outfalls or are identified in a regional water supply plan
developed pursuant to Section
373.709, F.S., shall have 15
bonus points added to the priority score after the adjustment under
subparagraph (e)2., above.
4.
Economic hardship. The extent of the economic hardship existing in a small
community to be served by the project shall be reflected in the priority score.
For a sponsor that qualifies as a small community with a financial hardship,
points shall be added to the priority score, using the formula 1000 divided by
the Affordability Index, after adjustment under subparagraphs (e)2. and (e)3.,
above.
(f) Priority List
Development. The priority list is developed at the public meeting and includes
the fundable, waiting, and planning portions. Projects that meet the
requirements of paragraph (b), above, compete for placement on the fundable or
waiting portions using a tiered ranking system. Tier 1 includes all projects
previously on the fundable portion which require an increase to an existing
loan, tier 2 includes new projects that receive a total priority score of 350
points or more, and tier 3 includes all other projects. Tier 1 is the highest
priority and tier 3 the lowest. Within each tier, projects are ranked in
priority score order with the highest score at the top of the tier. Once the
segment cap has been determined, the available funds are assigned to projects
in tiers 1 and 2 moving down the list until all projects have been assigned
funds, up to the lower of the requested amount or the segment cap, or until the
available funds are exhausted. The unfunded balance is then placed on the
waiting portion by tier then priority score order. If funds remain available,
they are assigned to projects in tier 3 until the funds are exhausted or all
projects have been funded. Projects that must be added to meet special
provisions of a federal capitalization grant shall be added to the bottom of
the fundable portion, bypassing projects that would otherwise be placed on the
fundable portion. Projects from tier 3 that do not receive any funding are
placed on the planning portion in alphabetical order. To receive funding,
projects on the planning portion must compete for funding at a subsequent
priority list public meeting.
(2) Allowable project costs. Categories of
allowable project costs include the following water pollution control
activities subject to such limitations for leveraged loans as are necessary to
maintain the tax-exempt status of bonds issued by the FWPCFC:
(a) Land purchased as necessary for
construction of water pollution control infrastructure. Funding shall be
limited to the appraised value of the fee simple interest of the acreage of
land to be purchased. The appraisal report must be less than 12 months old at
the time the construction loan application is received. If additional land is
acquired that is not necessary for construction, then the eligible funding
amount shall be the acreage of necessary land divided by the total acreage
purchased times the purchase price;
(b) Construction and related procurement and
other arrangements used to implement planned activities (such as a best
management practice);
(c)
Demolition and removal of existing structures;
(d) Contingency for project cost overruns
under subsection
62-503.300(4),
F.A.C.;
(e) Technical services
after bid opening or award of design/build or construction manager at risk
projects, and legal services resulting directly from the requirements of the
Department supplied supplementary conditions that are included in the bid
documents to comply with federal requirements, or legal services resulting from
contractor non-compliance with the construction contract;
(f) Costs associated with interim financing
for a sponsor whose project was adopted on the fundable or waiting portion of
the priority list, but proceeded without sufficient loan funds from the
Department;
(g) The purchase of a
domestic wastewater facility and its associated infrastructure, excluding the
value of land that is not necessary for operation of the facility. The project
sponsor shall demonstrate a substantial benefit to the community and
environment to be eligible for funding. Funding of a system acquisition shall
be limited to the system's fair market value;
(h) Technical services for soil and
hydrogeological tests, geotechnical evaluations, sewer system evaluations,
archaeological surveys, land surveys, and any other technical service deemed
necessary for the planning, design, and construction of a project and value
engineering services performed by a SAVE International Certified Value
Specialist. See the SAVE International web site at
http://www.value-eng.org/;
(i) Costs for project administration,
planning, or engineering under a planning or design loan;
(j) Project costs, excluding operational
costs, to implement best management practices for agricultural nonpoint source
water pollution control;
(k) For
sewer system evaluation studies, technical services for generating a sewer
system evaluation survey, inflow corrections including replacing clean out
caps, installing seals and dishes for manholes, and the televising/cleaning of
lines including point repairs as necessary;
(l) For I/I rehabilitation loans,
construction and related procurement used to implement the Department approved
planned activities for an I/I rehabilitation project;
(m) Preparation and implementation of an
asset management plan. To be eligible for reimbursement, the asset management
plan must meet the requirements of subsection
62-503.700(7),
F.A.C.;
(n) Constructed wetlands to
be used for the treatment of domestic wastewater.
(o) Project bidding/procurement costs
incurred under a design loan or construction loan; and
(p) The refinancing of unretired debt
principal for a qualifying sponsor whose project meets the environmental review
and procurement process of these rules, and only if in conjunction with a
construction project being funded by SRF; however, a project that is financed
with a loan from the Department shall not be refinanced by the Department at a
lower interest rate.
(3)
Ineligible project costs.
(a) Acquiring all
or part of an existing stormwater or water pollution control management system
except as allowed in paragraph
62-503.300(2)(g),
F.A.C.;
(b) Project facilities or
activities not included within the Department approved project scope;
(c) Costs for the use of the projects
sponsor's personnel or equipment in the planning, design, or construction of
project facilities or implementing of agricultural best management or
conservation practices;
(d) Costs
incurred after the project closeout has been conducted by the Department to
document project completion, final project costs, and adequacy of sponsor's
project files;
(e) Project
facilities or services for which the planning, design, construction and
procurement requirements of Rule
62-503.700, F.A.C., are not met;
(f) Water pollution control systems or
components thereof, under a leveraged loan, that service a private use to the
extent that the tax status of bonds issued by the FWPFC is
jeopardized;
(g) Acquisition of
sewer rights-of-way and easements;
(h) Service connections on private property
unless the project qualifies for funding as a result of section 319 of the
Act;
(i) Costs incurred before the
adoption of the project on the fundable or waiting portion of the priority
list;
(j) Any portion of a project
funded by an executed agreement from any regional, state, or federal funding
agency; and,
(k) Any other cost not
listed as allowable under subsection (2), above.
(4) Project contingency.
(a) Project contingency shall not exceed 10%
of the estimated sum of the construction costs and costs for allowable land.
The contingency shall be adjusted by the Department to 5% after procurement
contracts have been executed. There shall be no contingency for land when the
costs are known.
(b) The
contingency remaining after accounting for contract change orders shall be
retained by the Department when project closeout occurs.
(5) Financing rate.
(a) The financing rate shall be calculated as
follows except that the minimum financing rate shall be 0.2 percent and the
maximum financing rate shall be the market rate:
FR = MR - 4 + (4/(1+(100/AI)3)) -
1/Log(P)
Where:
FR = financing rate
MR = Market Rate
AI = Affordability Index
P = Population served or to be served by the sponsor
When bond proceeds are available for leveraged loans, the
market rate shall be the most recent rate at which bonds were sold by the
FWPCFC. When bond proceeds are not available, the market rate for interest
shall be established using the Thomson Publishing Corporation's "Bond Buyer"
20-Bond GO Index. The market rate, is established by the Department as of
January 1, April 1, July 1, and October 1 of each year and it is the average
weekly yield during the three months (3) immediately preceding the date of
determination. The average weekly yield is derived from the yields reported in
the "Bond Buyer" for the full weeks occurring during the three-month
period.
(b) The financing
rate shall be fixed for the principal amount of a planning, design, or
construction loan including any amendments and for the duration of the loan
repayment period. A planning loan may be rolled into a design loan, but the
financing rate remains fixed. A design loan cannot be rolled into a
construction loan. The financing rate shall be further adjusted by each of the
following for which the project qualifies, but the adjustments shall not reduce
the financing rate below 0.2 percent:
1.
Projects with a Department accepted and implemented asset management plan that
meets all requirements in subsection
62-503.700(7),
F.A.C., shall be eligible for a reduction in the financing rate if
implementation has been verified when the final disbursement request is
received or three (3) months prior to the first scheduled repayment, whichever
comes first. The financing rate shall be as calculated in paragraph
62-503.300(5)(a),
F.A.C., minus 0.1.
2. Projects that
qualify as a Green Projects as defined in subsection
62-503.200(22),
F.A.C., shall also be eligible for a reduction in the financing rate. For
projects that are entirely a Green Projects, the financing rate shall be as
calculated in paragraph
62-503.300(5)(a),
F.A.C., minus 0.1. For projects with components that do not qualify as a Green
Projects, the financing rate reduction shall be 0.1 times the Green Projects
component cost divided by the total as-bid construction cost. For these
projects the financing rate reduction shall be applied only after the project
has been bid.
3. Projects that
include a requirement for American Iron and Steel in accordance with Section
608 of the Act (33 USC ยง
1388) and projects that include a requirement
for Davis-Bacon wage rates as required in 29 CFR Part
5, Subpart A (7-1-2019
Edition) shall be eligible for a total reduction in the financing rate of 0.5.
The document 29 CFR Part
5, Subpart A is available from the Department's Clean
Water State Revolving Fund Program, 3900 Commonwealth Blvd., MS 3505,
Tallahassee, Florida 32399-3000, or at
http://www.flrules.org/Gateway/reference.asp?No=Ref-14073,
and is hereby adopted and incorporated by reference.
4. Project sponsors that agree to fund a
nontraditional project that is eligible under the Act but does not receive a
Clean Water State Revolving Fund loan, shall receive a financing rate reduction
such that the present worth of the savings is equivalent to the cost of the
project, up to a reduction in the financing rate of 0.5.
(c) The financing rate for a non-governmental
sponsor of a project that qualifies for funding as a result of section 319 or
320 of the Act shall be fifty (50%) percent of the current market
rate.
(6) Debt coverage
for non-governmental sponsors. A non-governmental sponsor of a project that
qualifies for funding as a result of section 319 or 320 of the Act shall
document that it has a current term debt and capital lease coverage ratio of at
least 1.15. This ratio shall have, as its numerator, net operations income plus
non-operating income plus depreciation plus interest on term debt (multi-year
debt) minus payroll and income taxes minus owner withdrawals; and, as its
denominator, the sum of scheduled payments on term debt and long-term leases.
This information shall be verified by the sponsor through a certified public
accountant (CPA).
Notes
Fla. Admin. Code Ann. R.
62-503.300
Rulemaking Authority 403.1835(10) FS. Law Implemented
403.1835 FS.
New 4-17-89, Amended 12-4-91, 2-23-94, Formerly
17-503.300, Amended 1-4-98, 7-1-99, 2-6-02, 7-29-04, 4-22-14, Amended by
Florida
Register Volume 48, Number 036, February 22, 2022 effective
3/9/2022.
New 4-17-89, Amended 12-4-91, 2-23-94, Formerly 17-503.300,
Amended 1-4-98, 7-1-99, 2-6-02, 7-29-04, 4-22-14,
3-9-22.