Fla. Admin. Code Ann. R. 62-610.462 - Reliability and Operator Staffing
(1)
The following reliability requirements shall apply. Facility reliability shall
have a minimum Class I reliability as described in paragraph
62-610.300(1)(a),
F.A.C. The Department shall approve alternative levels of treatment facility
reliability if the permittee provides reasonable assurances in the engineering
report that the facility will provide a level of reliability equivalent to
Class I reliability. Class I reliability shall not be required if a permitted
alternate treatment or discharge system exists which has sufficient capacity to
handle any reclaimed water flows which do not meet the performance criteria
established in the operating protocol.
(a)
Multiple aeration basins shall not be required for an oxidation ditch facility
to comply with Class I reliability requirements, if the following conditions
are met:
1. The construction permit
application was approved by the Department on or before April 5, 1989,
2. The treatment facility is not
being expanded; and,
3. All other
Class I reliability criteria are met.
(2) Except as provided in subsection
62-610.462(3) and
(4), F.A.C., the wastewater treatment
facility shall be staffed by a Class C or higher operator 24 hours per day, 7
days per week. The lead/chief operator shall be at minimum Class B, or higher
if required by Chapter 62-699, F.A.C.
(3) The minimum staffing requirement at the
wastewater treatment facility shall be reduced to staffing by a Class C or
higher operator 6 hours per day, 7 days per week, unless Chapter 62-699,
F.A.C., requires additional operator presence or a higher level of operator.
The lead/chief operator shall be at minimum Class C, or higher if required by
Chapter 62-699, F.A.C. This minimum staffing requirement shall be allowed only
in conjunction with at least one of the following.
(a) Diversion of acceptable quality reclaimed
water to the reuse system only during periods of operator presence.
(b) Other provisions for increased facility
reliability.
(4) If the
facility does not send reclaimed water to the public access reuse system on one
or both weekend days, the 7 day per week staffing requirement in subsection
62-610.462(3),
F.A.C., shall be reduced to 6 hours per day on each day reclaimed water is sent
to the public access reuse system. On weekend days when reclaimed water is
diverted to an alternative reuse or disposal system, a daily visit shall be
required.
Notes
Rulemaking Authority 403.051, 403.061, 403.087 FS. Law Implemented 403.021, 403.051, 403.061, 403.062, 403.085, 403.086, 403.087, 403.088 FS.
New 4-4-89, Amended 4-2-90, Formerly 17-610.462, Amended 1-9-96, 8-8-99, 4-1-21.