Fla. Admin. Code Ann. R. 62-610.491 - Additional Operation and Maintenance Requirements
(1) In addition to the operation and
maintenance requirements specified in Rule
62-610.320, F.A.C., and the
engineering report requirements specified in Rule
62-610.310, F.A.C., the
following requirements apply to reuse systems for irrigation in public access
areas.
(a) The permittee shall develop and
obtain Department approval of an operating protocol as discussed in Rules
62-610.320 and
62-610.463, F.A.C.
(b) The permittee shall develop and obtain
Department acceptance for a cross-connection prevention and inspection program
as discussed in Rule 62-610.469, F.A.C.
(c) As part of the permit application, the
applicant shall submit documentation of controls on individual users of
reclaimed water through detailed agreements (including copy of the agreement)
or by local ordinance (include copy of appropriate ordinance).
(d) A pretreatment program shall be developed
and implemented pursuant to Rule
62-610.330,
F.A.C.
(2) For new reuse
systems, items required by paragraphs
62-610.491(1)(a) and
(b), F.A.C., shall be approved or accepted
and implemented prior to placing the initial part, portion, or phase of the
reuse system into operation.
Notes
Rulemaking Authority 403.051, 403.061, 403.087 FS. Law Implemented 403.021, 403.051, 403.061, 403.062, 403.085, 403.086, 403.087, 403.088 FS.
New 4-4-89, Amended 4-2-90, Formerly 17-610.491, Amended 1-9-96, 4-1-21.
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.