Fla. Admin. Code Ann. R. 62-620.630 - Additional Permit Conditions for Domestic Wastewater Facilities
(1) Each domestic
wastewater facility permit which includes construction of new facilities, or
substantial modification of existing facilities, shall contain the permit
conditions listed in subsections (2) through (11), of this rule. These
conditions apply to an entire treatment plant or to individual unit processes,
as appropriate. If individual unit processes are to be placed into operation at
different times, the documentation required in subsection (2), of this rule,
shall be submitted for each unit process or combination of unit processes at
the time they are placed into operation. This rule does not apply to collection
and transmission systems which are permitted under Chapter 62-604,
F.A.C.
(2) Except for reuse systems
permitted under Part III of Chapter 62-610, F.A.C., the permittee shall submit
notification of completion of construction on DEP Form
62-620.910(12),
prior to placing the newly constructed or modified portion of an existing
facility into operation or any individual unit processes into operation, for
any purpose other than testing for leaks and equipment operation, and shall:
(a) Provide notification to the Department on
DEP Form 62-620.910(12),
that construction has been completed to the point where the facilities are
functionally complete. The notification shall be prepared by the project design
engineer or an engineer who has been retained by the permittee to provide
professional engineering services during the construction phase of project
completion. The engineer shall certify that the facilities have been
constructed substantially in accordance with the permit and the approved
preliminary design report and application materials or that any deviations will
not prevent the system from functioning in compliance with the requirements of
Chapter 62-600, F.A.C. The engineer shall note and explain substantial
deviations from the approved preliminary design report and application
materials. The notification shall be based upon onsite observation of
construction, scheduled and conducted by the engineer or by a project
representative under his direct supervision, for the purpose of determining
that the work proceeded in compliance with the approved preliminary design
report and application materials. This notification does not constitute a
certification of final completion of construction. Additional construction may
be needed to satisfy all conditions of the construction contract documents;
and,
(b) Provide notification to
the Department on DEP Form
62-620.910(13),
that a draft operation and maintenance manual pursuant to Chapters 62-600 and
62-610, F.A.C., as applicable, is available at a specified location. This
document shall contain instructions for the start-up, operation, and
maintenance of the facilities during this initial operation
period.
(3) Upon placing
a facility in operation, the facility shall be operated under the supervision
of an operator certified in accordance with Chapter 62-602, F.A.C. All facility
operations shall provide for the minimum care and maintenance of the facility
in accordance with Chapters 62-600 and 62-699, F.A.C.
(4) Reuse systems permitted under Chapter
62-610, Part III, F.A.C., shall not be placed in service for any purpose
without written approval from the Department. For projects identified in the
permit as being constructed in phases, written permission is only required for
the first phase. Written application shall be made using the appropriate form
from Rule 62-610.300, F.A.C. The following
items shall be submitted in support of a request to place a Part III reuse
system into operation:
(a) Notification of
completion pursuant to paragraph
62-620.630(2)(a),
F.A.C., except that certification shall be provided on DEP Form
62-610.300(4)(a)
3., instead of DEP Form
62-620.910(12);
(b) Notification that an appropriate draft
operation and maintenance manual, addition to the plant operation and
maintenance manual, or separate instruction booklet is available pursuant to
paragraph 62-620.630(2)(b),
F.A.C., except that certification shall be provided on DEP Form
62-610.300(4)(a)
3., instead of DEP Form
62-620.910(13);
(c) Documentation of approval of an operating
protocol pursuant to Chapter 62-610, F.A.C.; and,
(d) Documentation of acceptance of a
cross-connection control program pursuant to Chapter 62-610,
F.A.C.
(5) Upon placing a
facility in operation, effluent data shall be submitted to the Department on a
monthly basis and in accordance with Chapter 62-601, F.A.C.
(6) Upon placing a facility in operation,
residuals treatment, management, and disposal shall be consistent with methods
identified in the permit and other supporting documentation.
(7) Within six months after a facility is
placed in operation, the permittee shall provide written certification on DEP
Form 62-620.910(13),
that record drawings pursuant to Chapter 62-600, F.A.C., and that an
appropriate operation and maintenance manual pursuant to Chapters 62-600 and
62-610, F.A.C., as applicable, are available in a specified location.
(8) Domestic wastewater facility monitoring
requirements shall be established in accordance with Chapters 62-600, 62-601,
62-610, 62-611, and 62-640, F.A.C., as applicable.
(9) Operation and maintenance requirements
for domestic wastewater treatment facilities shall be established in accordance
with the applicable requirements of Chapters 62-600, 62-610, 62-611, 62-640,
and 62-699, F.A.C.
(10) Permits for
projects regulated under Chapter 62-610, Part III, F.A.C., shall include:
(a) Designation of the general areas to be
irrigated using reclaimed water.
(b) Designation of major users of reclaimed
water. A major user of reclaimed water is a site, such as a golf course, that
will use at least 0.1 mgd of reclaimed water.
(c) Identification of other approved uses of
reclaimed water and the conditions under which such uses may be practiced, such
as toilet flushing, fire protection, construction dust control, and aesthetic
uses.
(11) A reuse and
land application system permit shall contain limitations on flow and quality of
reclaimed water to be applied and shall list appropriate monitoring
requirements. Reuse and land application system permits shall also contain
limitations on flow and quality of water being discharged from the reuse and
land application system and shall list appropriate monitoring
requirements.
Notes
Rulemaking Authority 403.061, 403.087 FS. Law Implemented 403.051, 403.061, 403.062, 403.085, 403.086, 403.087, 403.088, 403.0885 FS.
New 11-29-94, Amended 10-23-00, 12-23-04.