Fla. Admin. Code Ann. R. 62B-33.013 - Permit Modifications, Time Extensions, Renewals, and Reissuances
(1) Requests for major changes or
modifications including additions, revisions, or structural modifications of
permitted projects or activities shall be reviewed in the same manner as the
initial application. Changes considered major are those changes that will
affect compliance with structural standards of this rule or which increase the
potential for adverse impacts.
(2)
A determination that minor changes or modifications, including minor additions,
revisions, or structural modifications of permitted projects or activities that
are within the scope of the permit, shall be made upon request of the
applicant. Minor additions, revisions, or structural modifications are those
changes which will not increase the risk of adverse impacts.
(3) The permittee or authorized agent may
request an extension of the permit expiration date by filing a written request
with the Department prior to the permit expiration date. If a request for a
time extension is completed pursuant to paragraph
62B-33.013(3)(a),
F.A.C., and received prior to the permit expiration date, the permit will be
valid until the Department acts upon the extension request. If a timely but
incomplete request for a time extension is received, construction must cease
upon the expiration date of the permit and shall not resume until the request
is complete or until the Department acts upon the request. Time extensions for
major structures and coastal armoring can be issued for periods of up to three
years, for other structures up to two years, and for permits for minor
structures or activities for up to one year. The total time extensions for
permits for major structures and coastal armoring shall not extend beyond three
years from the permit's original expiration date, beyond two years for other
structures and activities, and beyond one year for minor structures or
activities. The request shall be made using the time extension form entitled
"Application for a Permit Time Extension Pursuant to Rule
62B-33.013, F.A.C., " DEP Form
73-113 (Revised 7/22), which is hereby adopted and incorporated by reference. A
copy of the form can be obtained by contacting the Department of Environmental
Protection, 2600 Blair Stone Road, MS 3522, Tallahassee, Florida 32399-2400, at
https://floridadep.gov/water/coastal-construction-control-line/content/coastal-construction-control-line-cccl-forms
or by telephoning (850)245-2094.
(a) A written
request for a permit time extension shall include the following items:
1. The permit number,
2. The length of time requested,
3. A copy of a valid building permit or
current written evidence provided by the applicable county or municipality that
the authorization previously provided under paragraph
62B-33.008(1)(c),
F.A.C., shall remain in effect throughout the duration of the requested time
extension,
4. Reasonable assurance
that the activity can be completed within the time extension requested based on
a schedule for completion included with the request, that no significant change
in shoreline conditions has occurred since the original permit was issued, and
that the nature of the work has not changed; and,
5. A fee pursuant to Rule
62B-33.0085,
F.A.C.
(b) The Department
shall deny a request for a time extension if:
1. Shoreline or other conditions have changed
so that the project is no longer permittable under this rule chapter;
2. Application for a time extension is made
after the expiration date of the permit;
3. Construction has not started within the
five (5)-year period following the date of permit issuance for a major
structure;
4. The permit has
previously been extended to the limit allowed under this subsection or renewed
pursuant to subsection
62B-33.013(4),
F.A.C.; or
5. The time extension
request would extend the expiration date beyond three years from the permit's
original expiration date.
(4) If a permit has expired before the work
is complete, the applicant may apply in writing for a permit renewal provided
the request is made within six months of the original permit expiration date. A
permit renewal can be issued for periods of up to two years. Permit renewals
are not available if a time extension, pursuant to subsection
62B-33.013(3),
F.A.C., was previously issued. In order to obtain a renewal, the applicant must
provide information required in subparagraphs
62B-33.013(3)(a)
1. through 5., F.A.C. Time extensions are not authorized while a permit renewal
is in effect.
(5) If construction
is not complete after having been granted additional time by means of either a
time extension or a permit renewal, the permittee must submit an application
pursuant to Rule 62B-33.008, F.A.C., for a new or
reissued permit.
Notes
Rulemaking Authority 161.052(11), 161.053(20), 161.085(5) FS. Law Implemented 161.052(2), 161.053(2), (4), 161.085(1), (2) FS.
New 11-18-80, Amended 3-17-85, Formerly 16B-33.13, 16B-33.013, Amended 1-26-98, 8-27-00, 6-13-04, 5-31-07, 11-28-18.