The District will appoint a project manager who shall be
responsible for monitoring the project and the project agreement. The project
manager shall also be responsible for approving all reimbursement requests. The
project sponsor shall appoint a liaison agent, who will be a member of the
eligible applicant's staff, to act on its behalf in carrying out the terms of
the project agreement. Administration of the project will be as follows:
(1) Project Agreement: For each funded
project, the District and the project sponsor will enter into a project
agreement. The project agreement shall be executed and returned by the project
sponsor within six (6) months of the approval of the project funding and prior
to the release of program funds, setting forth the mutual obligations of the
parties concerning the project. The project agreement shall incorporate the
applicable policies and procedures of the program as outlined in this rule.
Project agreements will be for a two-year period with the possibility for one,
one-year extension. Any request for a one-year extension of funding shall
require submittal by the PROJECT SPONSOR of a request for extension to the
DISTRICT no later than July of fiscal year two of the approved project. This
request will then be considered by the DISTRICT Board, whose decision shall be
final. In review of these requests, the Board will take into consideration the
current status and progress of the project and the ability of the applicant to
complete the project within one additional year.
(2) Matching Funds: The project sponsor shall
clearly identify and enumerate the amount and source of the matching funds it
will be using to match the program funds supplied by the District for an
approved project. The project sponsor shall provide suitable evidence that it
has the matching funds available at the time the project agreement is
executed.
(3) Agreement
Modification: All proposed changes to the project agreement must be submitted
to the District in writing by the project sponsor accompanied by a statement of
justification for the proposed changes. All project agreement amendments shall
be approved by the District Board, except that the Executive Director may
approve a minor project agreement amendment for a project within a county with
the local District commissioner's concurrence. A minor project amendment shall
not change the approved project's category, result in a reallocation of more
than 35% of the approved funding of the project among project elements, nor
allow for a greater than 35% change in the project scale or scope of work.
Project agreement amendments will not include a change to the approved
project's location or a change in the approved project's purpose or project
type. Agreed changes shall be evidenced by a formal amendment to the project
agreement and shall be in compliance with these rules.
(4) Project Reporting: The liaison agent will
submit quarterly reports to the project manager summarizing the work
accomplished since the last report, problems encountered, percentage of project
completion and other appropriate information. These reports shall continue
throughout the length of the project period until completion of the project.
The report shall be submitted on Form 95-02, "Assistance Program Project
Quarterly Status Report, " dated 7-30-02, hereby incorporated by reference and
available at the District office. A Final Project Report shall be submitted at
the completion of the project and shall at minimum include: project summary,
photo of completed project, final cost, project benefits to the waterway and
location address.
(5) Reimbursement
Requests: The liaison agent may submit periodic reimbursement requests during
the project period in accordance with Rule
66B-2.011, F.A.C. The project
manager will approve or disapprove all reimbursement requests. The final
payment of program funds will be made upon certified completion of the project
by the District.
(6) Project
Inspection: Upon reasonable request, the project manager shall have the right
to inspect the project and any and all records relating to the
project.
(7) Project Completion:
The project shall be completed within three (3) years of the date of the
beginning of the District's first fiscal year for which the project was
approved. If the completion of a project is impacted by a declared state of
emergency and the Board waives this rule section, the extension of time granted
shall not exceed one additional three (3) year period.
(8) Project Completion Requirements: Upon
completion of the project, the liaison agent shall provide the following to the
project manager:
(a) A Project Completion
Certificate, FIND Form No. 90-13 (effective date 7-30-02), hereby incorporated
by reference and available from the District office, which certifies that the
project was completed in accordance with the project agreement and the final
project plans.
(b) A final
reimbursement request accompanied by all required billing statements and
vouchers.
(c) Photograph(s) showing
the installation of the sign required by Rule
66B-2.013, F.A.C.
(d) Photograph(s) of the completed project
clearly showing the program improvements.
(9) Project Completion Review: The project
manager will review the project completion package and will authorize or reject
the final reimbursement payment which will include all retained funds from
previous requests.