Ga. Comp. R. & Regs. R. 391-3-5-.06 - Source of Water Supply
(1)
Source of Water Supply. The source of water supply for all public
water systems must have the approval of the Division and a valid ground water
(Ground Water Use Act of 1972, as amended) or surface water (Georgia Water
Quality Control Act of 1977, as amended) withdrawal permit where applicable.
Beginning January 1, 1998, all owners and operators of new community public
water systems with groundwater sources must provide an approved back-up water
supply source, capable of providing adequate water service, if the primary
source becomes nonfunctional. The Director may waive this requirement for
systems with less than 25 service connections. Beginning December 1, 2009, any
new ground water source must provide treatment that reliably achieves at least
4-log (99.99%) treatment of viruses before or at the first customer.
(a) All sources of water supply must be
adequate as determined by the Division to meet anticipated growth. For human
consumption in a community water system, one hundred (100) gallons per day for
the projected population to be served at the end of the design period shall be
considered adequate.
1. Beginning January 1,
1998, all new sources constructed for water supply systems, that are required
to comply with the rules in this Chapter, shall be metered.
2. Beginning January 1, 1999, permitted water
systems shall meter their existing water supply sources, when required by the
Division or when the system's existing permit to operate a public water system
is renewed or modified.
(b) The water must be of such quality that
with reasonable treatment it will meet the Safe Drinking Water Rules of this
Chapter.
(c) Before approval of a
surface water source the following procedures and requirements must be met:
1. Raw water samples from the proposed source
shall be collected by the supplier or designee and submitted to a certified
laboratory for microbiological analysis for the period of time and frequency
specified by the Division.
2. The
supplier shall have the water from the proposed source analyzed for the
physical, chemical and radiological parameters specified by the Division in a
laboratory acceptable to the Division and shall furnish a copy of the results
of the analysis to the Division.
3.
For an impoundment source, allowance must be made for water losses including
required releases, evaporation, seepage and siltation. Available stream flow
and weather records must be used in estimating the yield of the
source.
4. For water supply
reservoirs, a reservoir management plan shall be developed in accordance with
Rule 391-3-16-.01(8).
5. A Source Water Assessment Plan (SWAP) for
the proposed surface water source intake must be developed in accordance with
the Division's Source Water Assessment and Protection Implementation
Plan for Public Drinking Water Sources, as outlined in Section
391-3-5-.42 of this
Chapter.
(d) Before
approval of a ground water source, whether from a well or a spring, the
following procedures and requirements must be met:
1. Raw water samples of the proposed source
shall be collected by the supplier and submitted to a laboratory certified by
the Division for microbiological analysis for a period of time and frequency
specified by the Division.
2. The
supplier shall, when directed by the Division, have the water from the proposed
source analyzed for the physical, chemical and radiological parameters
specified by the Division in a laboratory acceptable to the Division and shall
furnish a copy of the results of the analysis to the Division.
3. Any drilled well previously used as a
source of public water supply but inactive for three or more years and proposed
to be reactivated as a source of supply shall be test pumped and meet the
requirements of subparagraphs 1. and 2. of this paragraph.
4. A Source Water Assessment Plan (SWAP) for
the proposed ground water source must be developed, as applicable, in
accordance with the Division's Source Water Assessment and Protection
Implementation Plan for Public Drinking Water Sources, as outlined in
Section 391-3-5-.42 of
this Chapter.
(e) The
Division may direct that a ground water source be evaluated for the influence
of surface water. Within eighteen (18) months of Division notification that a
ground water source is under the direct influence of surface water, the
supplier shall install filtration treatment and may be required by the Division
to install additional treatment in accordance with subparagraph (a) of Rule
391-3-5-.09.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.