Ga. Comp. R. & Regs. R. 40-2-16-.13 - Water Supply
(1)
Approved System. The water supply for milkhouse and milking
operations must be:
(a) Approved as safe by
the applicable Government Water Control Authority, or
(b) For individual water systems,
constructed, maintained, and operated consistent with specifications outlined
in Appendix D and Appendix G of the current edition of the Pasteurized Milk
Ordinance, which are adopted by reference in
40-2-16-.31(7)(a).
(2)
Cross-Connections
Prohibited. No cross-connection may exist between a safe water supply
and any unsafe or questionable water supply or any other source of
pollution.
(3)
Backflow
Prevention. There must be no submerged inlets through which a safe water
supply may be contaminated.
(4)
Well Head Protected. The well or other source of water must be
located and constructed in such a manner that neither underground nor surface
contamination from any sewerage systems, privy or other source of pollution can
reach such water supply.
(5)
Disinfection Before Use.
(a) New
individual water supplies and water supply systems that have been repaired or
otherwise become contaminated must be thoroughly disinfected before being
placed in use.
(b) The supply must
be made free of the disinfectant by pumping to waste before any sample for
bacteriological testing is collected.
(6)
Containers and Tanks.
(a) All containers and tanks used in the
transportation of water must be sealed and protected from possible
contamination.
(b) These containers
and tanks must be subjected to a thorough cleaning and a bacteriological
treatment prior to filling with potable water to be used at the dairy
farm.
(c) To minimize the
possibility of contamination of the water during its transfer from the potable
tanks to the elevated or groundwater storage at the dairy farm, a suitable
pump, hose, and fittings must be provided.
(d) When the pump, hose, and fittings are not
being used, the outlets must be capped and stored in a suitable dust-proof
enclosure so as to prevent their contamination.
(e) The storage tank at the dairy farm must
be:
1. Constructed of impervious
material;
2. Provided with a dust
and rainproof cover; and
3.
Provided with an approved vent and roof hatch.
4. All new reservoirs or reservoirs which
have been cleaned must be disinfected prior to placing them into
service.
(7)
Water Sampling.
(a) Samples for
bacteriological examination of individual water supplies and reclaimed water
from heat exchanger processes or compressors on dairy farms must be taken:
1. Upon the initial approval of the physical
structure or water system;
2. When
any repair or alteration of the water supply system has been made;
and
3. At least:
(i) Once every three (3) year period for
individual water supplies, and
(ii)
At least once every six (6) month period for reclaimed water,
thereafter.
(iii) Individual water
supplies with buried well casing seals, installed prior to the adoption of
these Regulations, must be tested at least once every six (6) month
period.
(b)
Whenever such samples indicate either the presence of E. coli bacteria or
whenever the well casing, pump, or seal need replacing or repair, the well
casing and seal:
1. Must be brought above the
ground surface; and
2. Must comply
with all other applicable construction criteria of this Rule.
(c) When water is hauled to the
dairy farm, such water must be sampled for bacteriological examination at the
point of use and submitted to a laboratory at least four (4) times in separate
months during any consecutive six (6) month period.
(d) To determine if water samples have been
taken at the frequency established in this Rule, the interval shall include the
designated three (3) year or six (6) month period, respectively, plus the
remaining days of the month in which the sample is due.