Haw. Code R. § 11-265-1060 - Standards: Closed-vent systems and control devices
(a)
Owners and operators of closed-vent systems and control devices subject to this
subchapter shall comply with the provisions of section 11-265-1033.
(b)
(1) The
owner or operator of an existing facility who can not install a closed-vent
system and control device to comply with the provisions of this subchapter on
the effective date that the facility becomes subject to the provisions of this
subchapter must prepare an implementation schedule that includes dates by which
the closed-vent system and control device will be installed and in operation.
The controls must be installed as soon as possible, but the implementation
schedule may allow up to 30 months after the effective date that the facility
becomes subject to this subchapter for installation and startup.
(2) Any units that begin operation after
December 21, 1990, and are subject to the provisions of this subchapter when
operation begins, must comply with the rules immediately (i.e., must have
control devices installed and operating on startup of the affected unit); the
30-month implementation schedule does not apply.
(3) The owner or operator of any facility in
existence on the effective date of a statutory or regulatory amendment that
renders the facility subject to this subchapter shall comply with all
requirements of this subchapter as soon as practicable but no later than 30
months after the amendment's effective date. When control equipment required by
this subchapter can not be installed and begin operation by the effective date
of the amendment, the facility owner or operator shall prepare an
implementation schedule that includes the following information: Specific
calendar dates for award of contracts or issuance of purchase orders for the
control equipment, initiation of on-site installation of the control equipment,
completion of the control equipment installation, and performance of any
testing to demonstrate that the installed equipment meets the applicable
standards of this subchapter. The owner or operator shall enter the
implementation schedule in the operating record or in a permanent, readily
available file located at the facility.
(4) Owners and operators of facilities and
units that become newly subject to the requirements of this subchapter after
December 8, 1997 due to an action other than those described in paragraph
(b)(3) must comply with all applicable requirements immediately (i.e., must
have control devices installed and operating on the date the facility or unit
becomes subject to this subchapter; the 30-month implementation schedule does
not apply).