Haw. Code R. § 12-222.1-8 - Boiler external and non-boiler external piping

(a) Boiler external piping (BEP).
(1) BEP shall be designed, fabricated, installed and stamped in accordance with ASME BPVC Section I and ASME B31.1;
(2) Manufacturers of BEP shall possess an ASME certificate of authorization to use the certification mark with the "S" or "pp" designator;
(3) BEP may be installed by a manufacturer or contractor other than the manufacturer of the boiler, provided the organization has been issued a certificate of authorization to use the certification mark with the "S", "PP" or "A" designator; and in possession of a current and valid Hawaii contractors license as required in section 12-220-15;
(4) Prior to starting BEP installation, an application for installation shall be submitted to the department for an installation permit; and
(5) Welded repairs or alterations to boiler external piping shall be done by a company in possession of a valid NB "R" certificate of authorization.
(b) Non-boiler external piping (NBEP).
(1) NBEP design, fabrication, installation, alteration, or repair shall be done in accordance with the applicable provisions of the ASME BPVC, ASME B31.1, NBIC and this part;
(2) NBEP may be designed, fabricated, installed, altered, or repaired by organizations with valid ASME "S", "PP", or "A" designators or a NB "R" certificate of authorization, or organizations with a valid Hawaii NBEP certificate of authorization;
(3) Applicants whose quality control program have been reviewed, approved, and issued an NBEP certificate of authorization by the department shall be qualified to design, fabricate, install, alter, or repair NBEP within the provisions of ASME B31.1 and NBIC Part 3; and
(4) Application for authorization for design, fabrication, installation, alteration, or repair shall be submitted to the department as prescribed in section 12-220-9.1.

Notes

Haw. Code R. § 12-222.1-8
[Eff and comp 12/21/2019] (Auth: HRS § 397-4) (Imp: HRS § 397-4) Comp 9/8/2024

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.