Ill. Admin. Code tit. 77, § 855.170 - Project Manager Responsibilities, Air Sampling Professional Responsibilities and Laboratory Services
a)
Project Manager
1) The project manager shall
be licensed by the Department in accordance with Section
855.100. For asbestos abatement
projects in schools, the project manager shall be the building owner's
designated representative, and shall be responsible for carrying out the
following activities:
A) Assist in the
evaluation of bids and the selection of a contractor.
B) Ensure that all project activities are
conducted in accordance with the requirements of the Asbestos Abatement Act and
this Part and contract document.
C)
Be on-site whenever project activities are taking place.
D) Reject defective barriers and
decontamination enclosure systems.
E) Meet with the contractor daily to review
work progress, discuss problems and adjust procedures as appropriate.
F) Report on abatement activities to the
building owner and/or school board.
H) Enter the abatement project at least once
every two hours to observe ongoing removal of asbestos-containing
material.
2) For every
decontamination enclosure system, there shall be one project manager.
3) The project manager shall have the
authority to stop any job activities not performed in accordance with contract
specifications and any provisions of this Part. The building owner and
Department shall be notified verbally by the project manager within 24 hours
after a work stoppage. A written report shall be submitted to the building
owner with a description of the activity, reason for stoppage and possible
means for correcting the problem.
4) The project manager shall keep a daily log
of onsite observations concerning the contractor's compliance with activities
required under this Part. This log shall be legible and made available upon
request at all times to the school board or building owner, the
architect/engineer, contractor, and appropriate local, State and federal
agencies.
5) For each asbestos
abatement project, the project manager shall prepare a comprehensive final
report. The report shall be submitted to the school board or building owner,
the contractor, and the Department within 60 working days following completion
of final clearance air monitoring. The report shall contain the following items
submitted in the following order, with each item labeled:
A) Project Manager's Report Form provided by
the Department.
B) Items submitted
by the contractor under Section
855.350(a).
C) For clearance air samples, the location of
the sample, date of sample, start and end times of sampling, sampling air flow
rate, volume of air sampled, name and address of laboratory performing the
analysis, and name and signature of the analyst.
i) When final air clearance monitoring
samples are analyzed by a laboratory using transmission electron microscopy
(TEM), a copy of the National Voluntary Laboratory Accreditation Program
(NVLAP) certificate for airborne asbestos fibers analysis for the
laboratory.
ii) When final air
clearance air monitoring samples are analyzed by Phase Contrast Microscopy
(PCM) in a laboratory, a copy of Proficiency Analytical Testing (PAT) Program
year-to-date performance report for the laboratory. The year-to-date
performance report should be for the testing round completed closest to the
completion of the project, but prior to the completion of the
project.
iii) When final air
clearance air monitoring samples are analyzed by an analyst outside of a
laboratory, a copy of the report of performance testing under the (Asbestos
Analyst Report) AAR Program for the analyst for the testing round completed
prior to the completion of the project, but not after the completion of the
project.
D) Names,
license numbers and current training certificates for asbestos abatement
workers who conducted the abatement.
E) Name, address, and license number of
asbestos abatement contractor.
F)
Names, addresses, license numbers, and initial and current training
certificates for the project designer, project manager, and contractor's
supervisor(s), and signature of the project manager.
G) Name, signature, and license number of
each air sampling professional.
H)
Log of negative pressure measurements taken by the contractor for contained
areas. The readable tape from the monometer shall serve as the log.
I) Variance requests submitted to the
Department, and the Department's responses to those requests.
J) Locations, times and results of
background, personal, and area air samples taken prior to and during the
project.
K) A detailed description,
diagram or blueprint indicating the location of ACBM abated, locations of
barriers, and locations of decontamination enclosures.
L) A detailed description of the project,
including description of abatement methods employed, reasons for the project
and for selection of the abatement methods, description of types and amounts of
ACBM abated, and start and completion dates of the project.
M) Daily log of observations made by the
project manager, including description of project activities, documentation of
smoke testing of barriers by the contractor, documentation of post-abatement
visual inspection of each work area, and description of procedure used during
clearance air sampling.
N) Items
submitted by the contractor under Section
855.350(c) and
(d).
O) For cleaning performed in accordance with
Section 350.400(f)(1)(A), (D) and
(E), the names of persons performing the
cleaning, the date and locations of the cleaning, and the methods
used.
6) For each
asbestos abatement project, the project manager shall submit a completed
Project Manager's Report Form provided by the Department within ten working
days following completion of clearance air monitoring. A copy shall be inserted
as the first page in the project manager's report.
7) If more than one project manager serves on
a project, other than as specified below, the person who oversees the
completion of the project shall be responsible for the project report and for
submission of the Project Manager's Report Form to the Department. For projects
with multiple work areas, each overseen by a different project manager, each
project manager shall be responsible for the report and the Project Manager's
Report Form for the part of the project in the work area for which he or she
was responsible. However, one comprehensive report for the entire project is
acceptable.
b) Air
Sampling Professional (ASP)
1) The air
sampling professional shall be licensed by the Department in accordance with
Section 855.100. The air sampling
professional shall conduct or supervise all air sampling for the school board.
All projects greater than 160 square feet or 260 linear feet shall be analyzed
by Transmission Electron Microscopy (TEM). All other samples may be analyzed by
Phase Contrast Microscopy (PCM).
2)
Area sampling shall be conducted using collection media and procedures in
accordance with NIOSH method 7400. The following schedule shall be utilized for
air sampling during the project in addition to any OSHA compliance monitoring
required to be conducted by the contractor:
A)
Background air samples shall be collected and analyzed prior to the start of
project activities in order to determine background airborne fiber
concentrations. Samples shall be taken both inside and outside of the work area
to establish existing levels.
B)
The following schedule of samples shall be required on a daily basis once
abatement activities begin. The size of the abatement activity will have impact
on the number of samples necessary to monitor the contractor's activities. The
following are required minimums:
i) Two area
samples inside the work area;
ii)
One personal sample inside the work area;
iii) Two area samples outside the work area
in uncontaminated areas of the building, including one at the entrance to the
worker decontamination enclosure; and
iv) One area sample at each discharge from
negative pressure ventilation equipment to the outside of the
building.
C) Air
monitoring results shall be documented and retained on-site.
c) Analyst Services
1) When final clearance air monitoring
samples are anlyzed by a laboratory using TEM, the laboratory shall be
accredited by the NIOSH National Voluntary Laboratory Accreditation Program
(NVLAP) for airbone asbestos fiber analysis.
2) When final clearance air monitoring
samples are analyzed by PCM in a laboratory, the laboratory shall be considered
proficient in asbestos analysis by the American Industrial Hygiene Association
(AIHA) Proficiency Analytical Testing (PAT) Program for PCM.
3) When final air clearance air monitoring
samples are analyzed by an analyst outside of a laboratory, the analyst
analyzing the samples shall be considered proficient (board approved) by the
American Industrial Hygiene Association's (AIHA) Asbestos Analyst Registry
(AAR) Program.
4) The period of
time permitted between the collection of daily air samples and the availability
of results shall be less than 24 hours for samples collected during abatement
activities. Timetables for results of clearance air samples shall be
established by the school board or building owner.
d) Project Manager/Air Sampling Professional
Duties Combined
The project manager and air sampling professional shall be two separate individuals for each contained area. Duties may only be combined for abatement project activities when the contained area is less than or equal to 10,000 square feet or less than or equal to 1,500 linear feet of pipe insulation in one contained area and decontamination enclosure system.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.