326 IAC 6-6-3 - Compliance time tables
Authority: IC 13-1-1-4; IC 13-7-7
Affected: IC 13-1-1-1; IC 13-1-1-4; IC 13-7-7-2
Sec. 3.
(a) All
services and facilities subject to the requirements of this rule (326 IAC
6-6) shall be in compliance by December 22,
1984.
(b) In cases where an
existing service and facility cannot comply by December 22, 1984, the source or
facility shall submit to the commissioner a letter of intent to comply with
this rule (326 IAC 6-6) as expeditiously as
possible as well as a compliance plan including the following milestone dates:
(1) submittal of plans;
(2) start construction;
(3) completion of construction;
(4) achieving compliance; and
(5) submit performance results. Once the
commissioner has approved a source or facilities' compliance plan, the plan
shall be incorporated into the source or facilities' operation permit and shall
be submitted to the U.S. EPA as a SIP revision. Failure to operate within these
conditions shall be considered a violation of this rule (326 IAC
6-6).
(c) If emission limitations for a source or
facility are added to
326 IAC 6-6-4 or
326 IAC 6-6-5 after the original
promulgation date hereof or the emission limit applicable to a source or
facility is made more stringent by reason of amendments to this rule
(326 IAC 6-6), then such source
shall achieve compliance as soon as practicable but not later than specified by
the following schedule:
(1) Submittal of
plans and specifications within six (6) months after the date the source
becomes subject to the terms hereof, or the effective date of the amended rule
imposing a stricter limit (whichever date is applicable to a particular source
is hereafter referred to as the "effective date").
(2) Initiation of on-site construction or
installation within twelve (12) months after the effective date.
(3) Completion of on-site construction or
installation within twenty-four (24) months after the effective date.
(4) Achievement of compliance within
twenty-eight (28) months after the effective date.
(5) Submittal of performance results within
thirty (30) months of the effective date. An owner or operator may submit a
petition to the commissioner to establish an extended schedule for compliance
with this section. The petition shall include both a demonstration that
compliance cannot be achieved in accordance with this section and milestone
dates for purchases or construction necessary to achieve compliance. The
petition, if approved by the commissioner, shall be submitted to the U.S. EPA
as a revision to the SIP.