The following is incorporated by reference: 30 CFR Part 800, as in effect on July 1, 2010, with the following exceptions:
(1) Add to
30
CFR
800.40(c) a paragraph
(4) that shall read as follows:
(4) The
maximum liability under performance bonds applicable to a permit which may be
released at any time prior to the release of all acreage from the permit area
shall be calculated by multiplying the ratio between the acreage on which a
reclamation phase has been completed and the total acreage in the permit area,
times the total liability under performance bonds applicable to a permit, times
0.6 if reclamation phase I has been completed, or 0.25 if reclamation phase II
has been completed.
Acreage may be released from the permit area only after
reclamation phase III has been completed. The maximum performance bond
liability applicable to a permit which may be released at any time prior to the
completion of reclamation phase III on the entire permit area shall be
calculated by multiplying the ratio between the acreage on which reclamation
phase III has been completed and the total acreage in the permit area, times
the total liability under performance bonds applicable to a permit, times
0.15.
(2) Delete
from
30 CFR
800.60(a) the words
"authorized to do business in the United States" and insert the words
"authorized to do business in the State of Iowa".
(4) Delete from
30
CFR
800.40(a)(1) the words
"established in the regulatory program or".
(5) Delete from
30
CFR
800.40(c)(2) the words
"sections 515 and 515(b)(10) of the Act" and insert the words "Iowa Code
section
207.7". Delete also from
30
CFR
800.40(c)(2) the words
"performed pursuant to section 507(b)(16) of the Act" and insert the words
"information included in the permit application and obtained from the official
soil survey for the county in which the permit is located,".
(6) Delete from
30
CFR
800.40(h) the words
"section 513(b) of the Act" and insert the words "Iowa Code section
207.5".
(7) An application for bond
release shall not be considered filed until a written determination of
completeness for the bond release application has been provided to the
applicant by the division. The division will make a determination of
completeness for the bond release application within 30 days following receipt
of such application.
Notes
Iowa Admin. Code r. 27-40.51
ARC 9575B, IAB 6/29/11,
effective 8/3/11