Kan. Admin. Regs. § 28-45-5a - Storage facility permit application; renewal
(a) Each person that wants to construct and
operate a new storage facility shall submit a completed application for a
permit to the secretary on a form provided by the department, at least six
months before construction begins. Facility construction shall not begin until
the secretary has issued the permit.
(b) Each permittee of an existing storage
well or brine pond that is not authorized by a facility permit shall submit a
facility permit application within one year of the effective date of this
article of the department's regulations.
(c) Each application for a permit for a new
storage facility shall include the following information:
(1) Certification from a designated
signatory, as specified in
K.A.R.
28-45-9a ;
(2) siting requirements, as specified in
K.A.R.
28-45-10a ;
(3) an operations and maintenance plan, as
specified in
K.A.R.
28-45-12 ;
(4) an emergency response plan, as specified
in K.A.R.
28-45-13 ;
(5) an inventory balance plan, as specified
in K.A.R.
28-45-15 ;
(6) a subsidence monitoring plan, as
specified in
K.A.R.
28-45-16 ;
(7) a groundwater monitoring and quality
assurance plan, as specified in
K.A.R.
28-45-18 ;
(8) a report prepared by a professional
geologist that provides an evaluation of the local and regional geology and
hydrogeology;
(9) a narrative
interpretation by a professional geologist of at least one core collected
either within a half-mile radius of the proposed storage facility or at another
department-approved location; and
(10) a plan describing the coring interval,
coring procedures, and core testing for review and consideration for approval,
at least 60 days before the coring event. The following requirements shall
apply:
(A) The core data shall be made
available for review by the secretary upon request.
(B) The core shall be made available for
inspection by the department upon request for at least two years.
(C) Each permittee shall notify the
department, at least 30 days before core disposal.
(d) Upon the secretary's review of
each application for a permit for a storage facility, the applicant shall
receive one of the following:
(1) A facility
permit, if the application is approved; or
(2) a notice that the application has been
denied, if the applicant has not met the requirements of this article of the
department's regulations.
(e) Each permittee that wants to continue any
activity regulated by the facility permit shall submit a permit renewal
application to the secretary on a form provided by the department, at least six
months before the permit expires. Each renewal of a facility permit shall be
authorized for a period not to exceed 10 years.