Kan. Admin. Regs. § 5-13-10 - Time to construct the diversion works for a sand and gravel pit operation
(a) As used in
this regulation, "completion of diversion works" means that both of the
following have occurred:
(1) All equipment
necessary to begin to operate a sand and gravel operation, including the
hydraulic dredge, has been installed.
(2) Sufficient overburden has been excavated
to begin to expose the groundwater to evaporation.
(b) A reasonable time to construct the
diversion works for a sand and gravel pit operation shall be not less than one
full year following the approval of the application to appropriate water.
(c) For good cause shown by the
applicant, a reasonable extension of time to construct the diversion works
shall be allowed by the chief engineer if both of the following conditions are
met:
(1) The request for extension is filed
pursuant to the requirements of K.A.R. 5-3-7.
(2) The request for extension is accompanied
by the statutorily required filing fee.