Kan. Admin. Regs. § 5-40-72 - Construction inspection reports
The engineer responsible for the inspection required by K.A.R. 5-40-71 shall, within 30 days of the completion of the construction, repair, or modification of the dam and its appurtenances, submit to the chief engineer an inspection report containing the following items:
(a) Anotice of
completion showing the date on which construction, repair, or modification of
the dam and its appurtenances was completed;
(b) a statement indicating one of the
following:
(1) The dam and its appurtenances
were constructed, repaired, or modified substantially in accordance with the
permit and the approved plans and specifications; or
(2) the completed work varied from the permit
and the approved plans and specifications. A description of each variation
shall be provided;
(c)
a final survey of the completed dam and its appurtenances, including the
following:
(1) A profile of the top of the
dam;
(2) a profile of the
centerline of the auxiliary spillway or service spillway;
(3) a cross section at the control section of
the auxiliary spillway or service spillway;
(4) a cross section of the dam at its deepest
point;
(5) a cross section of the
dam at the primary spillway if that section is not near the deepest section of
the dam;
(6) the locations and
elevations of the inlet and the outlet of the primary spillway;
(7) the location and elevation of each drain
outlet; and
(8) the final
elevation and coordinates of each permanent benchmark; and
(d) a summary or a copy of the
daily inspection logs if required by the permit.